§175.230. Why are changes to purchased power costs not included in the procedure for adjusting electric power rates?
25 C.F.R. § 175.230
Changes to purchased power costs are not included in the procedure for adjusting electric power rates because unforeseen increases in the cost of purchased power are:
Not under our control;
Determined by current market rates; and
Subject to market fluctuations that can occur at an undetermined time and frequency.
Notes, amendments, and revision history
Authority
Authority: 5 U.S.C. 301; 25 U.S.C. 13; 25 U.S.C. 385c; 43 Stat. 475-76; 45 Stat. 210-13; 49 Stat. 1039-40; 49 Stat. 1822-23; 54 Stat. 422; 62 Stat. 269-73; 65 Stat. 254; 99 Stat. 319-20.
Source
Source: 83 FR 61119, Nov. 28, 2018, unless otherwise noted.