§401.500. Required notices to third parties and meeting with third parties.

24 C.F.R. § 401.500

(a)
General. The PAE must solicit, and document the consideration of, tenant and local community comments. As a minimum, the notices described in paragraphs (b), (c) and (f) of this section, in form and substance acceptable to HUD, must be provided. The PAE may require the owner to give the notices if permitted by HUD.
(b)
Notice of intent to restructure and consultation meeting.
(1)
This notice must include at a minimum:
(i)
The project, including its name and FHA Project Number;
(ii)
The responsible PAE and contact person, including the address and telephone number;
(iii)
The owner's notice of intent to restructure through the Mark-to-Market Program; and
(iv)
The date of expiration of the project-based assistance.
(2)
This notice must state how comments may be provided to the PAE regarding any of the following: the physical condition of the property, whether the rental assistance should be tenant-based or project-based, any proposed sale or transfer of the property, and other matters regarding the property and its management. The notice must establish the date, time, and place for a public meeting to be held no sooner than 20 days and no later than 40 days following the date of this notice. The public may provide written comments up to the date of the meeting.
(c)
Access to Restructuring Plan.
(1)
The PAE must make the Restructuring Plan available to the parties identified in § 401.501 at least 20 days before the PAE submits the Restructuring Plan to HUD (subject to any Federal, State, or local laws restricting access to any information in the Plan or related documents).
(2)
As soon as the PAE determines that the Restructuring Plan is substantively complete and ready for submission to HUD, notice of the following must be provided:
(i)
The location of the Plan for inspection and copying; and
(ii)
The date, time, and place of a public meeting to be held at least 10 days before the PAE submits the Plan to HUD.
(3)
When the PAE gives notice under this section, it must make the Plan available during normal business hours at the management office of the project, or if there is no such office, at another location specified by the PAE that is convenient to the tenants.
(d)
Meeting to discuss the Restructuring Plan. After the PAE has given notice under this section and at least 10 days before the PAE submits the Plan to HUD, the PAE must conduct a public meeting to obtain comments on the substantively completed Plan. The PAE must accept written comments through the date of the meeting.
(e)
Disposition of comments. The PAE must document and provide to HUD with the Restructuring Plan a summary of the disposition of all public comments.
(f)
Notice of completion of Restructuring Plan.
(1)
Within 10 days after the owner executes the Restructuring Commitment, notice must be provided that describes the completed Restructuring Plan and Restructuring Commitment. The PAE must make the completed Restructuring Plan and Restructuring Commitment available during normal business hours to the public at a place described in paragraph (c)(3) of this section, subject to Federal, State, or local laws restricting access to any information in any of these documents.
(2)
Within 10 days after a determination that the Restructuring Plan will not move forward for any reason, HUD or the PAE shall provide notice to affected tenants that describes the reasons for the failure of the Plan to move forward and the availability of tenant-based assistance under § 401.602(c).
Notes, amendments, and revision history

Amendments

[65 FR 15485, Mar. 22, 2000, as amended at 72 FR 66040, Nov. 26, 2007]

Authority

Authority: 12 U.S.C. 1715z-1 and 1735f-19(b); 42 U.S.C. 1437(c)(8), 1437f(t), 1437f note, and 3535(d).

Source

Source: 65 FR 15485, Mar. 22, 2000, unless otherwise noted.

Amendments

[65 FR 15485, Mar. 22, 2000, as amended at 72 FR 66040, Nov. 26, 2007]

§401.501. Delivery of notices and recipients of notices.

24 C.F.R. § 401.501

(a)
Whom must the owner or PAE notify? The PAE must notify, or ensure that the owner notifies, each tenant and any tenant organization for the project, and post a notice in the project, for all notices required by §§ 401.500 and 401.502.
(b)
Whom must the PAE notify? The PAE must notify:
(1)
The Chief Executive Officer of the unit of local government and the Executive Director of the Public Housing Authority with jurisdiction over the project location;
(2)
The recipient of any Outreach and Training Grant (OTAG) or Intermediary Technical Assistance Grant (ITAG) for the project location; and
(3)
Other appropriate neighborhood representatives and other affected parties.
Notes, amendments, and revision history

Amendments

[65 FR 15485, Mar. 22, 2000, as amended at 65 FR 53900, Sept. 6, 2000]

Authority

Authority: 12 U.S.C. 1715z-1 and 1735f-19(b); 42 U.S.C. 1437(c)(8), 1437f(t), 1437f note, and 3535(d).

Source

Source: 65 FR 15485, Mar. 22, 2000, unless otherwise noted.

Amendments

[65 FR 15485, Mar. 22, 2000, as amended at 65 FR 53900, Sept. 6, 2000]

§401.502. Notice requirement when debt restructuring will not occur.

24 C.F.R. § 401.502

(a)
PAE responsibility. If an owner of an eligible project requests a renewal of a section 8 contract without a Restructuring Plan under § 402.4 of this chapter, HUD or the PAE must notify, or ensure that the owner notifies, all parties identified in § 401.501 of the request and of:
(1)
The availability (as provided in § 401.500(c)(3)) of the following information:
(i)
The owner evaluation of physical condition (OEPC), or a comprehensive needs assessment (CNA) if used instead of an OEPC, as required by § 401.450 and § 402.6(a)(3) of this chapter;
(ii)
The market analysis required by § 402.6(a)(2) of this chapter, but without addresses (or other specific information indicating location) for comparable properties; and
(iii)
The items identified in § 401.500(b)(1)(i), (ii), and (iv); and
(2)
A procedure for submitting public comments regarding this information.
(b)
Expense and profit/loss information. The PAE should remove project expense, property valuation, and profit and loss information before disclosing any information obtained by the PAE directly from an owner or project manager, unless the owner has given written consent to disclosure with that information included.
(c)
Consideration of comments. The PAE must consider written public comments on the information listed in paragraph (a) of this section, if the comments are submitted within 30 days after giving notice under paragraph (a), and document the consideration for HUD. No public meeting is required.
Notes, amendments, and revision history

Amendments

[65 FR 15485, Mar. 22, 2000, as amended at 65 FR 53900, Sept. 6, 2000]

Authority

Authority: 12 U.S.C. 1715z-1 and 1735f-19(b); 42 U.S.C. 1437(c)(8), 1437f(t), 1437f note, and 3535(d).

Source

Source: 65 FR 15485, Mar. 22, 2000, unless otherwise noted.

Amendments

[65 FR 15485, Mar. 22, 2000, as amended at 65 FR 53900, Sept. 6, 2000]

§401.503. Access to information.

24 C.F.R. § 401.503

(a)
PAE responsibilities. The PAE must provide to parties entitled to notice under § 401.501 access to information obtained by the PAE about the project and its management if the PAE determines that such information is reasonably likely to contribute to effective participation by those parties in the restructuring process, or if HUD requires the PAE to provide access to the information. The PAE is not required to make public any information received from the owner or manager that the PAE reasonably characterizes as confidential or proprietary information that would not ordinarily be made public, except:
(1)
Owner evaluation of physical condition (OEPC), or a comprehensive needs assessment (CA) if used instead of an OEPC, as required by § 401.450;
(2)
Owner-prepared 1-year project rent analysis; and
(3)
As directed by HUD.
(b)
Information on expenses and profit/loss. Before disclosing any information, the PAE must remove any information obtained by the PAE directly from the owner or project manager that is related to project expenses, property valuation, or profit and loss, unless the owner gives written consent to disclosure with that information.
Notes, amendments, and revision history

Authority

Authority: 12 U.S.C. 1715z-1 and 1735f-19(b); 42 U.S.C. 1437(c)(8), 1437f(t), 1437f note, and 3535(d).

Source

Source: 65 FR 15485, Mar. 22, 2000, unless otherwise noted.