§630.705. Procedures.
23 C.F.R. § 630.705
An advance construction project shall meet the same requirements and be processed in the same manner as a regular Federal-aid project, except,
The FHWA authorization does not constitute any commitment of Federal funds on the project, and
The FHWA shall not reimburse the State until the project is converted under § 630.709.
[Reserved]
Notes, amendments, and revision history
Amendments
[60 FR 36993, July 19, 1995, as amended at 68 FR 60033, Oct. 21, 2003; 90 FR 40737, Aug. 21, 2025]
Source
Source: 60 FR 36993, July 19, 1995, unless otherwise noted.
Authority
Authority: 23 U.S.C. 106, 109, 112, 115, 315, and 402(a); sec. 1110, 1501, and 1503, Pub. L. 109-59, 119 Stat. 1144; Pub. L. 105-178, 112 Stat. 193; Pub. L. 104-59, 109 Stat. 582; Pub. L. 97-424, 96 Stat. 2106; Pub. L. 90-495, 82 Stat. 828; Pub. L. 85-767, 72 Stat. 896; Pub. L. 84-627, 70 Stat. 380; sections 1303 and 1405, Pub. L. 112-141, 126 Stat. 405; and 23 CFR 1.32 and 49 CFR 1.81 and 1.85.
Amendments
[60 FR 36993, July 19, 1995, as amended at 68 FR 60033, Oct. 21, 2003; 90 FR 40737, Aug. 21, 2025]