23 C.F.R. § 630.106
(a)
(1)
The State Department of Transportation (State DOT) must obtain an authorization to proceed from the FHWA before beginning work on any Federal-aid project. The State DOT may request an authorization to proceed in writing or by electronic mail for a project or a group of projects.
(2)
The FHWA will issue the authorization to proceed either through or after the execution of a formal project agreement with the State. The agreement can be executed only after applicable prerequisite requirements of Federal laws and implementing regulations and directives are satisfied. Except as provided in
paragraphs (c)(1) through (c)(4) of this section, the FHWA will obligate Federal funds in the project or group of projects upon execution of the project agreement.
(3)
The State's request that Federal funds be obligated shall be supported by a documented cost estimate that is based on the State's best estimate of costs.
(4)
The State shall maintain a process to adjust project cost estimates. For example, the process would require a review of the project cost estimate when the bid is approved, a project phase is completed, a design change is approved, etc. Specifically, the State shall revise the Federal funds obligated within 90 days after it has determined that the estimated Federal share of project costs has decreased by $250,000 or more.
(5)
The State shall review, on a quarterly basis, inactive projects (for the purposes of this subpart an “inactive project” means a project for which no expenditures have been charged against Federal funds for the past 12 months) with unexpended Federal obligations and shall revise the Federal funds obligated for a project within 90 days to reflect the current cost estimate, based on the following criteria:
(i)
Projects inactive for the past 12 months with unexpended balances more than $500,000,
(ii)
Projects inactive for the past 24 months with unexpended balances of $50,000 to $500,000, and
(iii)
Projects inactive for the past 36 months with unexpended balances less than $50,000.
(6)
If the State fails to comply with the requirements of paragraphs
(a)(3),
(4), or
(5) of this section, then the FHWA shall revise the obligations or take such other action as authorized by
23 CFR 1.36. The FHWA shall advise the State of its proposed actions and provide the State with the opportunity to respond before actions are taken. The FHWA shall not adjust obligations without a State's consent during the August redistribution process, August 1 to September 30.
(7)
For design-build projects, the execution or modification of the project agreement for final design and physical construction, and authorization to proceed, shall not occur until after the completion of the NEPA process. However, preliminary design (as defined in
23 CFR 636.103) and preliminary engineering may be authorized in accordance with this section.
(8)
For Construction Manager/General Contractor projects, the execution or modification of the project agreement for preconstruction services associated with final design and for construction services, and authorization to proceed with such services, shall not occur until after the completion of the NEPA process. However, preconstruction services associated with preliminary design may be authorized in accordance with this section.
(9)
For Indefinite Delivery/Indefinite Quantity projects, the execution or modification of the project agreement for final design or physical construction, and authorization to proceed, shall not occur until after the completion of the NEPA process.
Notes, amendments, and revision history
Amendments
[66 FR 23847, May 10, 2001, as amended at 71 FR 4995, Jan. 31, 2006; 72 FR 45336, Aug. 14, 2007; 81 FR 86942, Dec. 2, 2016; 85 FR 72931, Nov. 16, 2020]
Source
Source: 66 FR 23847, May 10, 2001, unless otherwise noted.
Authority
Authority: 23 U.S.C. 106, 109, 112, 115, 315, and 402(a); sec. 1110, 1501, and 1503, Pub. L. 109-59, 119 Stat. 1144; Pub. L. 105-178, 112 Stat. 193; Pub. L. 104-59, 109 Stat. 582; Pub. L. 97-424, 96 Stat. 2106; Pub. L. 90-495, 82 Stat. 828; Pub. L. 85-767, 72 Stat. 896; Pub. L. 84-627, 70 Stat. 380; sections 1303 and 1405, Pub. L. 112-141, 126 Stat. 405; and 23 CFR 1.32 and 49 CFR 1.81 and 1.85.
Amendments
[66 FR 23847, May 10, 2001, as amended at 71 FR 4995, Jan. 31, 2006; 72 FR 45336, Aug. 14, 2007; 81 FR 86942, Dec. 2, 2016; 85 FR 72931, Nov. 16, 2020]