§200.518. Major program determination. — Inbound Citations
2 C.F.R. § 200.518
Statutory Authority
Cited by 16 regulations in release Current.
Citations to 2 U.S.C. § 200.518 as a whole
-
(2) For purpose of this part, capital assets do not include intangible right-to-use assets (per GASB) and right-to-use operating lease assets (per FASB). For example, assets capitalized that recognize a lessee's right to control the use of property or equipment for a period of time under a lease contract. See § 200.465.Capital expenditures means expenditures to acquire capital assets or expenditures to make additions, improvements, modifications, replacements, rearrangements, reinstallations, renovations, or alterations to capital assets that materially increase their value or useful life.Central service cost allocation plan means the documentation identifying, accumulating, and allocating or developing billing rates based on the allowable costs of services provided by a State, local government, or Indian Tribe to its departments and agencies on a centralized basis. The costs of these services may be allocated or billed to users.Claim means, depending on the context, either:
-
(e) A Federal agency may request that an auditee have a particular Federal program audited as a major program in lieu of the Federal agency conducting or arranging for the additional audits. Such requests should be made at least 180 calendar days prior to the end of the fiscal year to be audited to allow for planning. After consultation with its auditor, the auditee should promptly respond to such a request by informing the Federal agency whether the program would otherwise be audited as a major program using the risk-based audit approach described in § 200.518 and, if not, the estimated incremental cost. The Federal agency must then promptly confirm to the auditee whether it wants the program audited as a major program. If the program is to be audited as a major program based upon this Federal agency request, and the Federal agency agrees to pay the full incremental costs, then the auditee must have the program audited as a major program. With approval of the Federal agency, a pass-through entity may use the provisions of this paragraph for a subrecipient.
-
An auditee that meets all of the following conditions for each of the preceding two audit periods must qualify as a low-risk auditee and be eligible for reduced audit coverage in accordance with § 200.518.
-
(1) All States, local governments, nonprofit organizations, and for-profit entities that are recipients or subrecipients of TAA Program funds must follow the audit requirements under 2 CFR 200.500 through 200.521 and 2 CFR 2900.20.
Citations to §200.518(b)
-
(a) The auditor must use a risk-based approach to determine which Federal programs are major programs. This risk-based approach must consider current and prior audit experience, oversight by Federal agencies and pass-through entities, and the inherent risk of the Federal program. The process described in paragraphs (b) through (h) of this section must be followed.
Citations to §200.518(b)(1)
-
(vii) An identification of major programs by listing each individual major program; however, in the case of a cluster of programs, only the cluster name as shown on the schedule of expenditures of Federal Awards is required; (viii) The dollar threshold used to distinguish between Type A and Type B programs, as described in § 200.518(b)(1) or (3) when a recalculation of the Type A threshold is required for large loan or loan guarantees; and
Citations to §200.518(b)(3)
-
(vii) An identification of major programs by listing each individual major program; however, in the case of a cluster of programs, only the cluster name as shown on the schedule of expenditures of Federal Awards is required; (viii) The dollar threshold used to distinguish between Type A and Type B programs, as described in § 200.518(b)(1) or (3) when a recalculation of the Type A threshold is required for large loan or loan guarantees; and
Citations to §200.518(c)
-
(a) The auditor must use a risk-based approach to determine which Federal programs are major programs. This risk-based approach must consider current and prior audit experience, oversight by Federal agencies and pass-through entities, and the inherent risk of the Federal program. The process described in paragraphs (b) through (h) of this section must be followed.
Citations to §200.518(d)
-
(a) The auditor must use a risk-based approach to determine which Federal programs are major programs. This risk-based approach must consider current and prior audit experience, oversight by Federal agencies and pass-through entities, and the inherent risk of the Federal program. The process described in paragraphs (b) through (h) of this section must be followed.
Citations to §200.518(e)
-
(a) The auditor must use a risk-based approach to determine which Federal programs are major programs. This risk-based approach must consider current and prior audit experience, oversight by Federal agencies and pass-through entities, and the inherent risk of the Federal program. The process described in paragraphs (b) through (h) of this section must be followed.
Citations to §200.518(f)
-
(a) The auditor must use a risk-based approach to determine which Federal programs are major programs. This risk-based approach must consider current and prior audit experience, oversight by Federal agencies and pass-through entities, and the inherent risk of the Federal program. The process described in paragraphs (b) through (h) of this section must be followed.
Citations to §200.518(g)
-
(a) The auditor must use a risk-based approach to determine which Federal programs are major programs. This risk-based approach must consider current and prior audit experience, oversight by Federal agencies and pass-through entities, and the inherent risk of the Federal program. The process described in paragraphs (b) through (h) of this section must be followed.
Citations to §200.518(h)
-
(a) The auditor must use a risk-based approach to determine which Federal programs are major programs. This risk-based approach must consider current and prior audit experience, oversight by Federal agencies and pass-through entities, and the inherent risk of the Federal program. The process described in paragraphs (b) through (h) of this section must be followed.