18 C.F.R. § 4.81
(b)
Exhibit 1— must contain a description of the proposed project, specifying and including, to the extent possible:
(1)
The number, physical composition, dimensions, general configuration and, where applicable, age and condition, of any dams, spillways, penstocks, powerhouses, tailraces, or other structures, whether existing or proposed, that would be part of the project;
(2)
The estimated number, surface area, storage capacity, and normal maximum surface elevation (mean sea level) of any reservoirs, whether existing or proposed, that would be part of the project;
(3)
The estimated number, length, voltage, interconnections, and, where applicable, age and condition, of any primary transmission lines whether existing or proposed, that would be part of the project
see [16 U.S.C. 796(11)];
(4)
The total estimated average annual energy production and installed capacity (provide only one energy and capacity value), the hydraulic head for estimating capacity and energy output, and the estimated number, rated capacity, and, where applicable, the age and condition, of any turbines and generators, whether existing or proposed, that would be part of the project works;
(5)
All lands of the United States that are enclosed within the proposed project boundary described under
paragraph (d)(3)(i) of this section, identified and tabulated on a separate sheet by legal subdivisions of a public land survey of the affected area, if available. If the project boundary includes lands of the United States, such lands must be identified on a completed land description form (FERC Form 587), provided by the Commission. The project location must identify any Federal reservation, Federal tracts, and townships of the public land surveys (or official protractions thereof if unsurveyed). A copy of the form must also be sent to the Bureau of Land Management state office where the project is located;
(6)
Any other information demonstrating in what manner the proposed project would develop, conserve, and utilize in the public interest the water resources of the region.
Notes, amendments, and revision history
Amendments
[Order 54, 44 FR 61336, Oct. 25, 1979, as amended by Order 123, 46 FR 9029, Jan. 28, 1981; 46 FR 11811, Feb. 11, 1981; Order 225, 47 FR 19056, May 3, 1982; Order 413, 50 FR 11685, Mar. 25, 1985; Order 2002, 68 FR 51120, Aug. 25, 2003; Order 655, 70 FR 33828, June 10, 2005; Order 699, 72 FR 45324, Aug. 14, 2007; Order 756, 77 FR 4894, Feb. 1, 2012; Order 857, 84 FR 7991, Mar. 6, 2019]
Authority
Authority: Federal Power Act, as amended 16 U.S.C. 792-828c; Department of Energy Organization Act, 42 U.S.C. 7101-7352; E.O. 12009, 42 FR 46267; Public Utility Regulatory Policies Act of 1978, 16 U.S.C. 2601-2645, unless otherwise noted.
Authority
Authority: 16 U.S.C. 791a-825r; 42 U.S.C. 7101-7352.
Source
Source: Order 141, 12 FR 8485, Dec. 19, 1947, unless otherwise noted.
Amendments
[Order 54, 44 FR 61336, Oct. 25, 1979, as amended by Order 123, 46 FR 9029, Jan. 28, 1981; 46 FR 11811, Feb. 11, 1981; Order 225, 47 FR 19056, May 3, 1982; Order 413, 50 FR 11685, Mar. 25, 1985; Order 2002, 68 FR 51120, Aug. 25, 2003; Order 655, 70 FR 33828, June 10, 2005; Order 699, 72 FR 45324, Aug. 14, 2007; Order 756, 77 FR 4894, Feb. 1, 2012; Order 857, 84 FR 7991, Mar. 6, 2019]