§4.71. Contents of application.
18 C.F.R. § 4.71
An application for license for transmission line only must contain the following information in the form specified.
Initial statement.
Required exhibits. The application must contain the following exhibits, as appropriate:
For any transmission line that, at the time the application is filed, is not constructed and is proposed to be connected to a licensed water power project with an installed generating capacity of more than 10 MW—Exhibits A, B, C, D, E, F, and G under § 4.41;
For any transmission line that, at the time the application is filed, is not constructed and is proposed to be connected to a licensed water power project with an installed generating capacity of 10 MW or less—Exhibits E, F, and G under § 4.61; and
For any transmission line that, at the time the application is filed, has been constructed and is proposed to be connected to any licensed water power project—Exhibits E, F, and G under § 4.61 of this chapter.
Notes, amendments, and revision history
Amendments
[Order 184, 46 FR 55942, Nov. 13, 1981, as amended by Order 413, 50 FR 11685, Mar. 25, 1985; Order 699, 72 FR 45324, Aug. 14, 2007; Order 877, 86 FR 42714, Aug. 5, 2021]
Authority
Authority: 16 U.S.C. 791a-825r; 42 U.S.C. 7101-7352.
Source
Source: Order 141, 12 FR 8485, Dec. 19, 1947, unless otherwise noted.
Amendments
[Order 184, 46 FR 55942, Nov. 13, 1981, as amended by Order 413, 50 FR 11685, Mar. 25, 1985; Order 699, 72 FR 45324, Aug. 14, 2007; Order 877, 86 FR 42714, Aug. 5, 2021]