§4.41. Contents of application. — Inbound Citations
18 C.F.R. § 4.41
Statutory Authority
Cited by 18 regulations in release Current.
Citations to 18 C.F.R. § 4.41 as a whole
-
(1) For amendment of a license for a water power project that, at the time the application is filed, is not constructed and is proposed to have a total installed generating capacity of more than 10 MW—Exhibits A, B, C, D, E, F, and G under § 4.41;
-
(iii) § 4.41;
-
(1) For any transmission line that, at the time the application is filed, is not constructed and is proposed to be connected to a licensed water power project with an installed generating capacity of more than 10 MW—Exhibits A, B, C, D, E, F, and G under § 4.41;
-
(ii) § 4.41 of this chapter (General instructions, initial statement, Exhibits A, B, C, D, F, and G);
-
(b) An applicant for an exemption under paragraph (a) must meet the requirements of subpart K or subpart J of part 4 of this chapter, and §§ 16.5, 16.6, 16.7, 16.8, 16.9(b) (1), (2) (except the requirement to comply with §§ 4.41, 4.51, or 4.61 of this chapter), 16.9(c), 16.10(a), 16.10(b), and 16.10(d).
-
-
(b) An applicant for an exemption must meet the requirements of, and will be processed in accordance with, subpart K or subpart J of part 4 of this chapter, and §§ 16.5, 16.8, 16.9(b)(2) (except the requirement to comply with §§ 4.41, 4.51, or 4.61 of this chapter), §§ 16.9(b)(3), 16.9(b)(4), 16.9(c), and 16.9(d).
-
Citations to §4.41(f)
-
(1) Any application must contain an Exhibit E conforming with the data and consultation requirements of § 4.41(f), if the application is for license for a water power project which has or is proposed to have a total installed generating capacity greater than 1.5 MW but not greater than 10 MW, and which:(i) Would use the water power potential of a dam and impoundment which, at the time of application, has not been constructed (see § 4.30(b)(15)); or(ii) Involves any repair, modification or reconstruction of an existing dam that would result in a significant change in the normal maximum surface area or elevation of an existing impoundment or involves any change in existing project works or operations that would result in a significant environmental impact (see § 4.30(b)(14)).
-
(ii) Submitting with its application an environmental report that meets the requirements of § 4.41(f) of this chapter, regardless of project size;
Citations to §4.41(g)
-
(f) Exhibit F is a set of drawings showing the structures and equipment of the small hydroelectric facility and must conform to the specifications of § 4.41(g) of this chapter.
-
(g) See § 4.41(g) of this chapter.
-
(e) See § 4.41(g) of this chapter.
-
(f) Exhibit F is a set of drawings showing the structures and equipment of the small conduit hydroelectric facility and must conform to the specifications of § 4.41(g) of this chapter.
Citations to §4.41(h)
-
(d) Exhibit G is a map of the project and boundary and must conform to the specifications of § 4.41(h) of this chapter.
-
(h) See § 4.41(h) of this chapter.
-
(f) See § 4.41(h) of this chapter.
-
(d) Exhibit G is a map of the project and boundary and must conform to the specifications of § 4.41(h) of this chapter.