§388.113. Critical Energy/Electric Infrastructure Information (CEII). — Inbound Citations

18 C.F.R. § 388.113

Cited by 29 regulations in release Current.

Citations to 18 C.F.R. § 388.113 as a whole

  • (7) Department of Energy (DOE) means all organizational entities that are part of the Executive Department created by Title II of the DOE Organization Act (Pub. L. 95-91, 91 Stat. 565, 42 U.S.C. 7101 et seq.). For purposes of this Part, the definition of DOE specifically excludes the Federal Energy Regulatory Commission, which has promulgated its own CEII procedures at 18 CFR 388.113.
  • (iii) “Procedures for obtaining access to Critical Energy Infrastructure Information (CEII) may be found at 18 CFR 388.113. Requests for access to CEII should be made to the Commission's CEII Coordinator.”
  • (e) The maps and drawings showing project location information and details of project structures must be filed in accordance with the Commission's instructions on submission of privileged materials and Critical Energy Infrastructure Information in §§ 388.112 and 388.113 of this chapter.
  • (C) “Procedures for obtaining access to Critical Energy Infrastructure Information (CEII) may be found at 18 CFR 388.113. Requests for access to CEII should be made to the Commission's CEII Coordinator.”
  • (b) As used in this section:
    Advanced Cybersecurity Technology means any technology, operational capability, or service, including computer hardware, software, or a related asset, that enhances the security posture of public utilities through improvements in the ability to protect against, detect, respond to, or recover from a cybersecurity threat (as defined in section 102 of the Cybersecurity Act of 2015 (6 U.S.C. 1501)).
    Advanced Cybersecurity Technology Information means information relating to Advanced Cybersecurity Technology or proposed Advanced Cybersecurity Technology that is generated by or provided to the Commission or another Federal agency. Pursuant to FPA section 219A(g), Advanced Cybersecurity Technology Information is considered to be Critical Electric Infrastructure Information.
    Critical Energy/Electric Infrastructure Information (CEII) has the same meaning as defined in 18 CFR 388.113.
    Electric Reliability Organization has the same meaning as defined in § 39.1 of this subchapter.
    Reliability Standard has the same meaning as defined in § 39.1 of this subchapter.
  • (g) Any person submitting documents containing critical energy infrastructure information must follow the procedures specified in § 388.113 of this chapter.
  • (5) Access to critical energy infrastructure information is subject to the requirements of § 388.113 of this chapter.
  • (iii) “Procedures for obtaining access to Critical Energy Infrastructure Information (CEII) may be found at 18 CFR 388.113. Requests for access to CEII should be made to the Commission's CEII Coordinator.”
  • (iii) “Procedures for obtaining access to Critical Energy Infrastructure Information (CEII) may be found at 18 CFR 388.113. Requests for access to CEII should be made to the Commission's CEII Coordinator.”
  • (a) By following the procedures specified in this section, any person submitting a document to the Commission may request privileged treatment for some or all of the information contained in a particular document that it claims is exempt from the mandatory public disclosure requirements of the Freedom of Information Act, 5 U.S.C. 552 (FOIA), and should be withheld from public disclosure. For the purposes of the Commission's filing requirements, non-CEII subject to an outstanding claim of exemption from disclosure under FOIA will be referred to as privileged material. The rules governing CEII are contained in § 388.113.

Citations to §388.113(c)

  • (4) is defined at FPA section 215(a)(3), with designation criteria codified at 18 CFR 388.113(c). CEII means information related to critical electric infrastructure, or proposed critical electrical infrastructure, generated by or provided to FERC or another Federal agency, other than classified national security information, that is designated as CEII by FERC or the Secretary pursuant to section 215A(d) of the FPA. Such term includes information that qualifies as critical energy infrastructure information under FERC's regulations.
  • (1) If this section requires an applicant to reveal Critical Energy Infrastructure Information (CEII), as defined in § 388.113(c) of this chapter, to any person, the applicant shall omit the CEII from the information made available and insert the following in its place:
    (i) A statement that CEII is being withheld;
    (ii) A brief description of the omitted information that does not reveal any CEII; and
    (iii) “Procedures for obtaining access to Critical Energy Infrastructure Information (CEII) may be found at 18 CFR 388.113. Requests for access to CEII should be made to the Commission's CEII Coordinator.”
  • (9) If this section requires an applicant to reveal Critical Energy Infrastructure Information (CEII), as defined by § 388.113(c) of this chapter, to any person, the applicant shall follow the procedures set out in § 4.32(k).
  • (h) If this section requires an applicant to reveal Critical Energy Infrastructure Information (CEII), as defined by § 388.113(c) of this chapter, to any person, the applicant shall follow the procedures set out in § 4.32(k).
  • If any action required by this part requires a potential Applicant or Applicant to reveal Critical Energy Infrastructure Information, as defined by § 388.113(c) of this chapter, to the public, the Applicant must follow the procedures set out in § 4.32(k) of this chapter.
  • (i) If paragraph (d) of this section requires an applicant to reveal Critical Energy Infrastructure Information (CEII), as defined in § 388.113(c) of this chapter, to any person, the applicant shall omit the CEII from the information made available and insert the following in its place:
    (A) A statement that CEII is being withheld;
    (B) A brief description of the omitted information that does not reveal any CEII; and
    (C) “Procedures for obtaining access to Critical Energy Infrastructure Information (CEII) may be found at 18 CFR 388.113. Requests for access to CEII should be made to the Commission's CEII Coordinator.”
  • (j) If this section requires an applicant to reveal Critical Energy Infrastructure Information (CEII), as defined by § 388.113(c) of this chapter, to any person, the applicant shall follow the procedures set out in § 16.7(d)(7).
  • (1) If the instructions in Form No. 715 require a utility to reveal Critical Energy Infrastructure Information (CEII), as defined in § 388.113(c) of this chapter, to any person, the utility shall omit the CEII from the information made available and insert the following in its place:
    (i) A statement that CEII is being withheld;
    (ii) A brief description of the omitted information that does not reveal any CEII; and
    (iii) “Procedures for obtaining access to Critical Energy Infrastructure Information (CEII) may be found at 18 CFR 388.113. Requests for access to CEII should be made to the Commission's CEII Coordinator.”
  • (1) If this section requires an applicant to reveal Critical Energy Infrastructure Information (CEII), as defined in § 388.113(c) of this chapter, to the public, the applicant shall omit the CEII from the information made available and insert the following in its place:
    (i) A statement that CEII is being withheld;
    (ii) A brief description of the omitted information that does not reveal any CEII; and
    (iii) “Procedures for obtaining access to Critical Energy Infrastructure Information (CEII) may be found at 18 CFR 388.113. Requests for access to CEII should be made to the Commission's CEII Coordinator.”
  • (a) All exhibits specified must accompany each application when tendered for filing. Together with each exhibit applicant must provide a full and complete explanation of the data submitted, the manner in which it was obtained, and the reasons for the conclusions derived from the exhibits. If the Commission determines that a formal hearing upon the application is required or that testimony and hearing exhibits should be filed, the Secretary will promptly notify the applicant that submittal of all exhibits and testimony of all witnesses to be sponsored by the applicant in support of his case-in-chief is required. Submittal of these exhibits and testimony must be within 20 days from the date of the Secretary's notice, or any other time as the Secretary will specify. Exhibits, except exhibits F, F- 1, G, G-I, and G-II, must be submitted to the Commission on electronic media as prescribed in § 385.2011 of this chapter. Receipt and delivery point information required in various exhibits must be labeled with a location point name and code in conformity with the location name and code the pipeline has adopted in conformance with § 284.13(f) of this chapter. Intervenors and persons becoming intervenors after the date of the Secretary's notice must be advised by the applicant of the afore-specified exhibits and testimony, and must be furnished with copies upon request. If this section requires an applicant to reveal Critical Energy Infrastructure Information (CEII), as defined by § 388.113(c) of this chapter, to any person, the applicant shall follow the procedures set out in § 157.10(d).
    (1) If applicant is not an individual, a conformed copy of its articles of incorporation and bylaws, or other similar documents.
    (2) For each State where applicant is authorized to do business, a statement showing the date of authorization, the scope of the business applicant is authorized to carry on and all limitations, if any, including expiration dates and renewal obligations. A conformed copy of applicant's authorization to do business in each State affected shall be supplied upon request.
    (3) A list of the names and business addresses of applicant's officers and directors, or similar officials if applicant is not a corporation.
    (4) If applicant or any of its officers or directors, directly or indirectly, owns, controls, or holds with power to vote, 10 percent or more of the outstanding voting securities of any other person or organized group of persons engaged in production, transportation, distribution, or sale of natural gas, or of any person or organized group of persons engaged in the construction or financing of such enterprises or operations, a detailed explanation of each such relationship, including the percentage of voting strength represented by such ownership of securities. If any person or organized group of persons, directly or indirectly, owns, controls, or holds with power to vote, 10 percent or more of the outstanding voting securities of applicant—a detailed explanation of each such relationship.
    (5) A list of other applications and filings under sections 1, 3, 4 and 7 of the Natural Gas Act filed by the applicant which are pending before the Commission at the time of the filing of an application and which directly and significantly affect the application filed, including an explanation of any material effect the grant or denial of those other applications and filings will have on the application and of any material effect the grant or denial of the application will have on those other applications and filings.
    (6) Unless shown on Exhibit G or elsewhere, a geographical map of suitable scale and detail showing, and appropriately differentiating between all of the facilities proposed to be constructed, acquired or abandoned and existing facilities of applicant, the operation or capacity of which will be directly affected by the proposed facilities or the facilities proposed to be abandoned. This map, or an additional map, shall clearly show the relationship of the new facilities to the applicant's overall system and shall include:
    (A) Main-line industrial customers, gas pipeline or distribution systems, showing towns and communities served and to be served at wholesale and retail, and
    (7) An environmental report as specified in §§ 380.3 and 380.12 of this chapter. Applicant must submit all appropriate revisions to Exhibit F-I whenever route or site changes are filed. These revisions should identify the locations by mile post and describe all other specific differences resulting from the route or site changes, and should not simply provide revised totals for the resources affected.
    (8) A flow diagram showing daily design capacity and reflecting operating conditions with only existing facilities in operation. A second flow diagram showing daily design capacity and reflecting operating conditions with both proposed and existing facilities in operation. Both flow diagrams shall include the following for the portion of the system affected:
    (i) Diameter, wall thickness, and length of pipe installed and proposed to be installed and the diameter and wall thickness of the installed pipe to which connection is proposed.
    (ii) For each proposed new compressor station and existing station, the size, type and number of compressor units, horsepower required, horsepower installed and proposed to be installed, volume of gas to be used as fuel, suction and discharge pressures, and compression ratio.
    (iv) Pressures and volumes of gas at each intake and take-off point and at the beginning and terminus of the existing and proposed facilities and at the intake or take-off point of the existing facilities to which the proposed facilities are to be connected.
    (9) If Exhibit G does not reflect the maximum deliveries which applicant's existing and proposed facilities would be capable of achieving under most favorable operating conditions with utilization of all facilities, include an additional diagram or diagrams to depict such maximum capabilities. If the horsepower, pipelines, or other facilities on the segment of applicant's system under consideration are not being fully utilized due, e.g., to capacity limitation of connecting facilities or because of the need for standby or spare equipment, the reason for such nonutilization shall be stated.
    (10) Exhibits G and G-I shall be accompanied by a statement of engineering design data in explanation and support of the diagrams and the proposed project, setting forth:
    (i) Assumptions, bases, formulae, and methods used in the development and preparation of such diagrams and accompanying data.
    (ii) A description of the pipe and fittings to be installed, specifying the diameter, wall thickness, yield point, ultimate tensile strength, method of fabrication, and methods of testing proposed.
    (iv) Type, capacity, and location of each natural gas storage field or facility, and of each dehydration, desulphurization, natural gas liquefaction, hydrocarbon extraction, or other similar plant or facility directly attached to the applicant's system, indicating which of such plants are owned or operated by applicant, and which by others, giving their names and addresses.
    (v) If the daily design capacity shown in Exhibit G is predicated upon an ability to meet each customer's maximum contract quantity on the same day, explain the reason for such coincidental peak-day design. If the design day capacity shown in Exhibit G is predicated upon an assumed diversity factor, state that factor and explain its derivation.
    (vi) The maximum allowable operating pressure of each proposed facility for which a certificate is requested, as permitted by the Department of Transportation's safety standards. The applicant shall certify that it will design, install, inspect, test, construct, operate, replace, and maintain the facilities for which a certificate is requested in accordance with Federal safety standards and plans for maintenance and inspection or shall certify that it has been granted a waiver of the requirements of the safety standards by the Department of Transportation in accordance with the provisions of section 3(e) of the Natural Gas Pipeline Safety Act of 1968. Pertinent details concerning the waiver shall be set forth.
    (11) A statement by applicant describing:
    (i) Those production areas accessible to the proposed construction that contain sufficient existing or potential gas supplies for the proposed project; and
    (iii) This paragraph (a)(11) shall cease to have effect on December 5, 2026, unless the Commission determines that the cessation deadline should be extended to a date not more than 5 years in the future after offering the public an opportunity to provide input on the costs and benefits of this paragraph (a)(11) and considering that input. The Commission will publish a document in the Federal Register announcing its determination and revising or removing this paragraph (a)(11) accordingly.
    (12) A system-wide estimate of the volumes of gas to be delivered during each of the first 3 full years of operation of the proposed service, sale, or facilities and during the years when the proposed facilities are under construction, and actual data of like import for each of the 3 years next preceding the filing of the application, together with:
    (i) Names and locations of customer companies and municipalities, showing the number of residential, commercial, firm industrial, interruptible industrial, residential space-heating, commercial space-heating, and other types of customers for each distribution system to be served at retail or wholesale; and the names and locations of each firm and interruptible direct industrial customer whose estimated consumption totals 10,000 Mcf or more in any calendar month or 100,000 Mcf or more per year together with an explanation of the end use to which each of these industrial customers will put the gas.
    (ii) Applicant's total annual and peak day gas requirements by classification of service in paragraph (a)(11)(i) of this section, divided as follows: Gas requirements for each distribution area where gas is sold by applicant at retail; for each wholesale customer; for all main line direct industrial customers; and company use and unaccounted-for gas, for both the applicant and each wholesale customer.
    (iii) Total past and expected curtailments of service by the applicant and each wholesale customer proposing to receive new or additional supplies of gas from the project, all to be listed by the classifications of service in paragraph (a)(12)(i) of this section.
    (iv) Explanation and derivation of basic factors used in estimating future requirements, including, for example: Peak-day and annual degree-day deficiencies, annual load factors of applicant's system and of its deliveries to its proposed customers; individual consumer peak-day and annual consumption factors for each class of consumers, with supporting historical data; forecasted saturation of space-heating as related to past experience; and full detail as to all other sources of gas supply available to applicant and to each of its customers, including manufacturing facilities and liquid petroleum gas.
    (v) Conformed copy of each contract, letter of intent or other agreement for sale or transportation of natural gas proposed by the application. Indicate the rate to be charged. If no agreements have been made, indicate the basis for assuming that contracts will be consummated and that service will be rendered under the terms contemplated in the application.
    (vi) A full description of all facilities, other than those covered by the application, necessary to provide service in the communities to be served, the estimated cost of such facilities, by whom they are to be constructed, and evidence of economic feasibility.
    (vii) A copy of each market survey made within the past three years for such markets as are to receive new or increased service from the project applied for.
    (viii) A statement showing the franchise rights of applicant or other person to distribute gas in each community in which service is proposed.
    (ix) When an application requires a statement of total peak-day or annual market requirements of affiliates, whose operations are integrated with those of applicant, to demonstrate applicant's ability to provide the service proposed or to establish a gas supply, estimates and data required by this paragraph (a)(12)(ix) shall also be stated in like detail for such affiliates.
    (x) When the proposed project is for service which would not decrease the life index of the total system gas supply by more than one year, the data required in paragraphs (a)(12)(i) to (ix), inclusive, of this section need be submitted only as to the particular market to receive new or additional service.
    (13) A statement identifying each Federal authorization that the proposal will require; the Federal agency or officer, or State agency or officer acting pursuant to delegated Federal authority, that will issue each required authorization; the date each request for authorization was submitted; why any request was not submitted and the date submission is expected; and the date by which final action on each Federal authorization has been requested or is expected.
    (14) A detailed estimate of total capital cost of the proposed facilities for which application is made, showing cost of construction by operating units such as compressor stations, main pipelines, laterals, measuring and regulating stations, and separately stating the cost of right-of-way, damages, surveys, materials, labor, engineering and inspection, administrative overhead, fees for legal and other services, allowance for funds used during construction, and contingencies. Include a brief statement indicating the source of information used as the basis for the above estimate. If not otherwise set forth, submit data on preliminary bids, if any, for the proposed facilities and recent experienced cost data for facilities of similar character.
    (15) Plans for financing the proposed facilities for which the application is filed, together with:
    (i) A description of the class (e.g., commercial paper, long-term debt, preferred stock) and cost rates for securities expected to be issued with construction period and post- operational sources of financing separately identified.
    (ii) Statement of anticipated cash flow, including provision during the period of construction and the first 3 full years of operation of proposed facilities for interest requirements, dividends, and capital requirements.
    (iv) Comparative pro forma balance sheets and income statements for the period of construction and each of the first 3 full years of operation, giving effect to the proposed construction and proposed financing of the project.
    (v) Any additional data and information upon which applicant proposes to rely in showing the adequacy and availability of resources for financing its proposed project.
    (vi) In instances for which principal operations of the company have not commenced or where proposed rates for services are developed on an incremental basis, a brief statement explaining how the applicant will determine the actual allowance for funds used during construction (AFUDC) rate, or if a rate is not to be used, how the applicant will determine the actual amount of AFUDC to be capitalized as a component of construction cost, and why the method is appropriate under the circumstances.
    (16) A concise statement setting forth arrangements for supervision, management, engineering, accounting, legal, or other similar service to be rendered in connection with the construction or operation of the project, if not to be performed by employees of applicant, including reference to any existing or contemplated agreements therefor, together with:
    (i) See Exhibit D, paragraph (a)(4) of this section.
    (ii) Conformed copies of all construction, engineering, management, and other similar service agreements or contracts in any way operative with respect to construction, operation, or financing of facilities which are the subject of the application or will be applicable under system operations.
    (17) When the estimated revenues and expenses related to a proposed facility will significantly affect the operating revenues or operating expenses of an applicant, there shall be submitted a system-wide statement for the last year preceding the proposed construction or service and pro forma system-wide and incremental statements for each of the first three full years of operation of the proposed facilities, showing:
    (i) Gas system annual revenues and volumes of natural gas related thereto, subdivided by classes of service, and further subdivided by sales to direct industrial customers, sales to other gas utilities, and other sales, indicating billing quantities used for computing charges, e.g., actual demands, billing demands, volumes, heat-content adjustment or other determinants. In addition, if enlargement or extension of facilities is involved, the revenues attributable solely to the proposed facilities shall be stated separately, and the basis and data used in such computation shall be clearly shown.
    (ii) Gas system annual operating expenses classified in accordance with the Commission's Uniform System of Accounts for Natural Gas Companies; the annual depreciation, depletion, taxes, utility income, and resulting rate of return on net investment in gas plant including working capital. In addition if enlargement or extension of facilities is involved, the cost of service attributable solely to the proposed facilities shall be stated separately with supporting data.
    (iii) When the data required in paragraphs (a)(17)(i) and (ii) of this section is not submitted, applicant shall provide in lieu thereof a statement in sufficient detail to show clearly the effect on the operating revenues and operating expenses of the estimated revenues and expenses related to the proposed facility.
    (18) Depreciation and depletion rates to be established, the method of determination and the justification therefor.
    (A) Identification of the applicable presently effective rate schedules, when no additional tariff filings will be required, or
    (B) When changes are required in applicant's presently effective tariff, or if applicant has no tariff, pro forma copies of appropriate changes in or additions to the effective tariff or a pro forma copy of the new gas tariff proposed, or
    (C) Such statement shall clearly show whether such rate results from negotiation, cost-of-service determination, competitive factors or others, and shall give the nature of any studies which have been made in connection therewith.
    (ii) When new rates or changes in present rates are proposed or when the proposed facilities will result in a material change in applicant's average cost of service, such statement shall be accompanied by supporting data showing:
    (A) System cost of service for the first calendar year of operation after the proposed facilities are placed in service.
    (B) An allocation of such costs to each particular service classification, with the basis for each allocation clearly stated.
  • In addition to the exhibits required by § 157.14, every application involving acquisition of facilities must be accompanied by the exhibits listed below. Together with each exhibit applicant must provide a full and complete explanation of the data submitted, the manner in which it was obtained, and the reasons for the conclusions derived from the exhibits, unless the applicant includes a statement identifying the schedule and rate containing the required information and data filed as prescribed in § 385.2011 of this chapter. If the Commission determines that a formal hearing upon the application is required or that testimony and hearing exhibits should be filed, the Secretary will promptly notify the applicant that submittal of all the exhibits and testimony of all witnesses to be sponsored by the applicant in support of his case-in-chief is required. Submittal of these exhibits and testimony must be within 20 days from the date of the Secretary's notice, or any other time specified by the Secretary in the notice. Sections 157.6(a) and 385.2011 of this chapter will govern the submissions required to be furnished to the Commission. Interveners and persons becoming interveners after the date of the Secretary's notice must be advised by the applicant of the afore-specified exhibits and testimony, and must be furnished with copies upon request. If this section requires an applicant to reveal Critical Energy Infrastructure Information (CEII), as defined by § 388.113(c) of this chapter, to any person, the applicant shall follow the procedures set out in § 157.10(d).
  • (4) If paragraphs (d)(1) or (d)(2) of this section require an applicant to reveal Critical Energy Infrastructure Information (CEII), as defined by § 388.113(c) of this chapter, to any person, the applicant shall follow the procedures set out in § 157.10(d).
  • (6) If paragraph (d)(3) of this section requires an applicant to reveal Critical Energy Infrastructure Information (CEII), as defined by § 388.113(c) of this chapter, to any person, the applicant shall follow the procedures set out in § 157.10(d).
  • (a) Receive and review all requests for CEII as defined in § 388.113(c) of this chapter.

Citations to §388.113(c)(1)

  • (2) If a transmission provider discloses, in a manner contrary to the requirements of § 358.6, non-public transmission customer information, critical energy infrastructure information (CEII) as defined in § 388.113(c)(1) of this chapter or any successor provision, or any other information that the Commission by law has determined is to be subject to limited dissemination, the transmission provider must immediately post notice on its Web site that the information was disclosed.

Citations to §388.113(g)(1)

  • (5) If any requester not described above in paragraphs (g)(1) through (4) of this section has a particular need for information designated as CEII, the requester may request the information using the following procedures:
    (i) The request must contain the following:
    (A) Requester's name (including any other name(s) which the requester has used and the dates the requester used such name(s)), title, address, and telephone number; and the name, address, and telephone number of the person or entity on whose behalf the information is requested;
    (B) A detailed Statement of Need, which must state: The extent to which a particular function is dependent upon access to the information; why the function cannot be achieved or performed without access to the information; an explanation of whether other information is available to the requester that could facilitate the same objective; how long the information will be needed; whether or not the information is needed to participate in a specific proceeding (with that proceeding identified); and an explanation of whether the information is needed expeditiously.
    (C) An executed non-disclosure agreement as described in paragraph (h)(2) of this section;
    (D) A signed statement attesting to the accuracy of the information provided in the request; and
    (E) A requester shall provide his or her date and place of birth upon request, if it is determined by the CEII Coordinator that this information is necessary to process the request.
    (ii) A requester who seeks the information on behalf of all employees of an organization should clearly state that the information is sought for the organization, that the requester is authorized to seek the information on behalf of the organization, and that all individuals in the organization that have access to the CEII will agree to be bound by a non-disclosure agreement that must be executed.
    (iii) After the request is received, the CEII Coordinator will determine if the information is CEII, and, if it is, whether to release the CEII to the requester. The CEII Coordinator will balance the requester's need for the information against the sensitivity of the information. If the requester is determined to be eligible to receive the information requested, the CEII Coordinator will determine what conditions, if any, to place on release of the information.
    (iv) If the CEII Coordinator determines that the CEII requester has not demonstrated a valid or legitimate need for the CEII or that access to the CEII should be denied for other reasons, this determination may be appealed to the General Counsel pursuant to § 388.110. The General Counsel will decide whether the information is properly classified as CEII, which by definition is exempt from release under FOIA, and whether the Commission should in its discretion make such CEII available to the CEII requester in view of the requester's asserted legitimacy and need.
    (v) Once a CEII requester has been verified by Commission staff as a legitimate requester who does not pose a security risk, his or her verification will be valid for the remainder of that calendar year. Such a requester is not required to provide detailed information about himself or herself with subsequent requests during the calendar year. He or she is also not required to file a non-disclosure agreement with subsequent requests during the calendar year because the original non-disclosure agreement will apply to all subsequent releases of CEII.
    (vi) An organization that is granted access to CEII pursuant to paragraph (g)(5)(ii) of this section may seek to add additional individuals to the non-disclosure agreement within one (1) year of the date of the initial CEII request. Such an organization must provide the names of the added individuals to the CEII Coordinator and certify that notice of each added individual has been given to the submitter. Any newly added individuals must execute a supplement to the original non-disclosure agreement indicating their acceptance of its terms. If there is no written opposition within five business days of notifying the CEII Coordinator and the submitter concerning the addition of any newly added individuals, the CEII Coordinator will issue a standard notice accepting the addition of these names to the non-disclosure agreement. If the submitter files a timely opposition with the CEII Coordinator, the CEII Coordinator will issue a formal determination addressing the merits of such opposition. If an organization that is granted access to CEII pursuant to paragraph (g)(5)(ii) of this section wants to add new individuals to its non-disclosure agreement more than one year after the date of its initial CEII request, the organization must submit a new CEII request pursuant to paragraph (g)(5)(ii) of this section and a new non-disclosure agreement for each new individual added.
    (vii) The CEII Coordinator will attempt to respond to the requester under this section according to the timing required for responses under the FOIA in § 388.108(c).
    (viii) Fees for processing CEII requests will be determined in accordance with § 388.109.
    (ix) Nothing in this section should be construed as requiring the release of proprietary information, personally identifiable information, cultural resource information, information on rare species of plants and animals, and other comparable data protected by statute or any privileged information, including information protected by the deliberative process privilege.

Citations to §388.113(g)(2)

  • (5) If any requester not described above in paragraphs (g)(1) through (4) of this section has a particular need for information designated as CEII, the requester may request the information using the following procedures:
    (i) The request must contain the following:
    (A) Requester's name (including any other name(s) which the requester has used and the dates the requester used such name(s)), title, address, and telephone number; and the name, address, and telephone number of the person or entity on whose behalf the information is requested;
    (B) A detailed Statement of Need, which must state: The extent to which a particular function is dependent upon access to the information; why the function cannot be achieved or performed without access to the information; an explanation of whether other information is available to the requester that could facilitate the same objective; how long the information will be needed; whether or not the information is needed to participate in a specific proceeding (with that proceeding identified); and an explanation of whether the information is needed expeditiously.
    (C) An executed non-disclosure agreement as described in paragraph (h)(2) of this section;
    (D) A signed statement attesting to the accuracy of the information provided in the request; and
    (E) A requester shall provide his or her date and place of birth upon request, if it is determined by the CEII Coordinator that this information is necessary to process the request.
    (ii) A requester who seeks the information on behalf of all employees of an organization should clearly state that the information is sought for the organization, that the requester is authorized to seek the information on behalf of the organization, and that all individuals in the organization that have access to the CEII will agree to be bound by a non-disclosure agreement that must be executed.
    (iii) After the request is received, the CEII Coordinator will determine if the information is CEII, and, if it is, whether to release the CEII to the requester. The CEII Coordinator will balance the requester's need for the information against the sensitivity of the information. If the requester is determined to be eligible to receive the information requested, the CEII Coordinator will determine what conditions, if any, to place on release of the information.
    (iv) If the CEII Coordinator determines that the CEII requester has not demonstrated a valid or legitimate need for the CEII or that access to the CEII should be denied for other reasons, this determination may be appealed to the General Counsel pursuant to § 388.110. The General Counsel will decide whether the information is properly classified as CEII, which by definition is exempt from release under FOIA, and whether the Commission should in its discretion make such CEII available to the CEII requester in view of the requester's asserted legitimacy and need.
    (v) Once a CEII requester has been verified by Commission staff as a legitimate requester who does not pose a security risk, his or her verification will be valid for the remainder of that calendar year. Such a requester is not required to provide detailed information about himself or herself with subsequent requests during the calendar year. He or she is also not required to file a non-disclosure agreement with subsequent requests during the calendar year because the original non-disclosure agreement will apply to all subsequent releases of CEII.
    (vi) An organization that is granted access to CEII pursuant to paragraph (g)(5)(ii) of this section may seek to add additional individuals to the non-disclosure agreement within one (1) year of the date of the initial CEII request. Such an organization must provide the names of the added individuals to the CEII Coordinator and certify that notice of each added individual has been given to the submitter. Any newly added individuals must execute a supplement to the original non-disclosure agreement indicating their acceptance of its terms. If there is no written opposition within five business days of notifying the CEII Coordinator and the submitter concerning the addition of any newly added individuals, the CEII Coordinator will issue a standard notice accepting the addition of these names to the non-disclosure agreement. If the submitter files a timely opposition with the CEII Coordinator, the CEII Coordinator will issue a formal determination addressing the merits of such opposition. If an organization that is granted access to CEII pursuant to paragraph (g)(5)(ii) of this section wants to add new individuals to its non-disclosure agreement more than one year after the date of its initial CEII request, the organization must submit a new CEII request pursuant to paragraph (g)(5)(ii) of this section and a new non-disclosure agreement for each new individual added.
    (vii) The CEII Coordinator will attempt to respond to the requester under this section according to the timing required for responses under the FOIA in § 388.108(c).
    (viii) Fees for processing CEII requests will be determined in accordance with § 388.109.
    (ix) Nothing in this section should be construed as requiring the release of proprietary information, personally identifiable information, cultural resource information, information on rare species of plants and animals, and other comparable data protected by statute or any privileged information, including information protected by the deliberative process privilege.

Citations to §388.113(g)(3)

  • (5) If any requester not described above in paragraphs (g)(1) through (4) of this section has a particular need for information designated as CEII, the requester may request the information using the following procedures:
    (i) The request must contain the following:
    (A) Requester's name (including any other name(s) which the requester has used and the dates the requester used such name(s)), title, address, and telephone number; and the name, address, and telephone number of the person or entity on whose behalf the information is requested;
    (B) A detailed Statement of Need, which must state: The extent to which a particular function is dependent upon access to the information; why the function cannot be achieved or performed without access to the information; an explanation of whether other information is available to the requester that could facilitate the same objective; how long the information will be needed; whether or not the information is needed to participate in a specific proceeding (with that proceeding identified); and an explanation of whether the information is needed expeditiously.
    (C) An executed non-disclosure agreement as described in paragraph (h)(2) of this section;
    (D) A signed statement attesting to the accuracy of the information provided in the request; and
    (E) A requester shall provide his or her date and place of birth upon request, if it is determined by the CEII Coordinator that this information is necessary to process the request.
    (ii) A requester who seeks the information on behalf of all employees of an organization should clearly state that the information is sought for the organization, that the requester is authorized to seek the information on behalf of the organization, and that all individuals in the organization that have access to the CEII will agree to be bound by a non-disclosure agreement that must be executed.
    (iii) After the request is received, the CEII Coordinator will determine if the information is CEII, and, if it is, whether to release the CEII to the requester. The CEII Coordinator will balance the requester's need for the information against the sensitivity of the information. If the requester is determined to be eligible to receive the information requested, the CEII Coordinator will determine what conditions, if any, to place on release of the information.
    (iv) If the CEII Coordinator determines that the CEII requester has not demonstrated a valid or legitimate need for the CEII or that access to the CEII should be denied for other reasons, this determination may be appealed to the General Counsel pursuant to § 388.110. The General Counsel will decide whether the information is properly classified as CEII, which by definition is exempt from release under FOIA, and whether the Commission should in its discretion make such CEII available to the CEII requester in view of the requester's asserted legitimacy and need.
    (v) Once a CEII requester has been verified by Commission staff as a legitimate requester who does not pose a security risk, his or her verification will be valid for the remainder of that calendar year. Such a requester is not required to provide detailed information about himself or herself with subsequent requests during the calendar year. He or she is also not required to file a non-disclosure agreement with subsequent requests during the calendar year because the original non-disclosure agreement will apply to all subsequent releases of CEII.
    (vi) An organization that is granted access to CEII pursuant to paragraph (g)(5)(ii) of this section may seek to add additional individuals to the non-disclosure agreement within one (1) year of the date of the initial CEII request. Such an organization must provide the names of the added individuals to the CEII Coordinator and certify that notice of each added individual has been given to the submitter. Any newly added individuals must execute a supplement to the original non-disclosure agreement indicating their acceptance of its terms. If there is no written opposition within five business days of notifying the CEII Coordinator and the submitter concerning the addition of any newly added individuals, the CEII Coordinator will issue a standard notice accepting the addition of these names to the non-disclosure agreement. If the submitter files a timely opposition with the CEII Coordinator, the CEII Coordinator will issue a formal determination addressing the merits of such opposition. If an organization that is granted access to CEII pursuant to paragraph (g)(5)(ii) of this section wants to add new individuals to its non-disclosure agreement more than one year after the date of its initial CEII request, the organization must submit a new CEII request pursuant to paragraph (g)(5)(ii) of this section and a new non-disclosure agreement for each new individual added.
    (vii) The CEII Coordinator will attempt to respond to the requester under this section according to the timing required for responses under the FOIA in § 388.108(c).
    (viii) Fees for processing CEII requests will be determined in accordance with § 388.109.
    (ix) Nothing in this section should be construed as requiring the release of proprietary information, personally identifiable information, cultural resource information, information on rare species of plants and animals, and other comparable data protected by statute or any privileged information, including information protected by the deliberative process privilege.

Citations to §388.113(g)(4)

  • (5) If any requester not described above in paragraphs (g)(1) through (4) of this section has a particular need for information designated as CEII, the requester may request the information using the following procedures:
    (i) The request must contain the following:
    (A) Requester's name (including any other name(s) which the requester has used and the dates the requester used such name(s)), title, address, and telephone number; and the name, address, and telephone number of the person or entity on whose behalf the information is requested;
    (B) A detailed Statement of Need, which must state: The extent to which a particular function is dependent upon access to the information; why the function cannot be achieved or performed without access to the information; an explanation of whether other information is available to the requester that could facilitate the same objective; how long the information will be needed; whether or not the information is needed to participate in a specific proceeding (with that proceeding identified); and an explanation of whether the information is needed expeditiously.
    (C) An executed non-disclosure agreement as described in paragraph (h)(2) of this section;
    (D) A signed statement attesting to the accuracy of the information provided in the request; and
    (E) A requester shall provide his or her date and place of birth upon request, if it is determined by the CEII Coordinator that this information is necessary to process the request.
    (ii) A requester who seeks the information on behalf of all employees of an organization should clearly state that the information is sought for the organization, that the requester is authorized to seek the information on behalf of the organization, and that all individuals in the organization that have access to the CEII will agree to be bound by a non-disclosure agreement that must be executed.
    (iii) After the request is received, the CEII Coordinator will determine if the information is CEII, and, if it is, whether to release the CEII to the requester. The CEII Coordinator will balance the requester's need for the information against the sensitivity of the information. If the requester is determined to be eligible to receive the information requested, the CEII Coordinator will determine what conditions, if any, to place on release of the information.
    (iv) If the CEII Coordinator determines that the CEII requester has not demonstrated a valid or legitimate need for the CEII or that access to the CEII should be denied for other reasons, this determination may be appealed to the General Counsel pursuant to § 388.110. The General Counsel will decide whether the information is properly classified as CEII, which by definition is exempt from release under FOIA, and whether the Commission should in its discretion make such CEII available to the CEII requester in view of the requester's asserted legitimacy and need.
    (v) Once a CEII requester has been verified by Commission staff as a legitimate requester who does not pose a security risk, his or her verification will be valid for the remainder of that calendar year. Such a requester is not required to provide detailed information about himself or herself with subsequent requests during the calendar year. He or she is also not required to file a non-disclosure agreement with subsequent requests during the calendar year because the original non-disclosure agreement will apply to all subsequent releases of CEII.
    (vi) An organization that is granted access to CEII pursuant to paragraph (g)(5)(ii) of this section may seek to add additional individuals to the non-disclosure agreement within one (1) year of the date of the initial CEII request. Such an organization must provide the names of the added individuals to the CEII Coordinator and certify that notice of each added individual has been given to the submitter. Any newly added individuals must execute a supplement to the original non-disclosure agreement indicating their acceptance of its terms. If there is no written opposition within five business days of notifying the CEII Coordinator and the submitter concerning the addition of any newly added individuals, the CEII Coordinator will issue a standard notice accepting the addition of these names to the non-disclosure agreement. If the submitter files a timely opposition with the CEII Coordinator, the CEII Coordinator will issue a formal determination addressing the merits of such opposition. If an organization that is granted access to CEII pursuant to paragraph (g)(5)(ii) of this section wants to add new individuals to its non-disclosure agreement more than one year after the date of its initial CEII request, the organization must submit a new CEII request pursuant to paragraph (g)(5)(ii) of this section and a new non-disclosure agreement for each new individual added.
    (vii) The CEII Coordinator will attempt to respond to the requester under this section according to the timing required for responses under the FOIA in § 388.108(c).
    (viii) Fees for processing CEII requests will be determined in accordance with § 388.109.
    (ix) Nothing in this section should be construed as requiring the release of proprietary information, personally identifiable information, cultural resource information, information on rare species of plants and animals, and other comparable data protected by statute or any privileged information, including information protected by the deliberative process privilege.