§35.28. Non-discriminatory open access transmission tariff. — Inbound Citations
18 C.F.R. § 35.28
Statutory Authority
Cited by 6 regulations in release Current.
Citations to 18 C.F.R. § 35.28 as a whole
-
(d) To demonstrate a lack of vertical market power, a Seller that owns, operates or controls transmission facilities, or whose affiliates own, operate or control transmission facilities, must have on file with the Commission an Open Access Transmission Tariff, as described in § 35.28; provided, however, that a Seller whose foreign affiliate(s) own, operate or control transmission facilities outside of the United States that can be used by competitors of the Seller to reach United States markets must demonstrate that such affiliate either has adopted and is implementing an Open Access Transmission Tariff as described in § 35.28, or otherwise offers comparable, non-discriminatory access to such transmission facilities.
Citations to §35.28(g)(1)
-
(ii) A public utility that is approved as a regional transmission organization under § 35.34, or that is not approved but begins to operate regional markets for electric energy or ancillary services after December 29, 2008, must comply with Order No. 719 and the provisions of paragraphs (g)(1) through (g)(5) of this section before beginning operations.
Citations to §35.28(g)(2)
-
(ii) A public utility that is approved as a regional transmission organization under § 35.34, or that is not approved but begins to operate regional markets for electric energy or ancillary services after December 29, 2008, must comply with Order No. 719 and the provisions of paragraphs (g)(1) through (g)(5) of this section before beginning operations.
Citations to §35.28(g)(3)
-
(ii) A public utility that is approved as a regional transmission organization under § 35.34, or that is not approved but begins to operate regional markets for electric energy or ancillary services after December 29, 2008, must comply with Order No. 719 and the provisions of paragraphs (g)(1) through (g)(5) of this section before beginning operations.
Citations to §35.28(g)(4)
-
(ii) A public utility that is approved as a regional transmission organization under § 35.34, or that is not approved but begins to operate regional markets for electric energy or ancillary services after December 29, 2008, must comply with Order No. 719 and the provisions of paragraphs (g)(1) through (g)(5) of this section before beginning operations.
Citations to §35.28(g)(5)
-
(ii) A public utility that is approved as a regional transmission organization under § 35.34, or that is not approved but begins to operate regional markets for electric energy or ancillary services after December 29, 2008, must comply with Order No. 719 and the provisions of paragraphs (g)(1) through (g)(5) of this section before beginning operations.