§35.1. Application; obligation to file rate schedules, tariffs and certain service agreements. — Inbound Citations

18 C.F.R. § 35.1

Cited by 6 regulations in release Current.

Citations to 18 C.F.R. § 35.1 as a whole

  • (a) The letter of a public utility transmitting to the Commission for filing an initial rate schedule or tariff shall list the documents submitted with the filing; give the date on which the service under that rate schedule or tariff is expected to commence; state the names and addresses of those to whom the rate schedule or tariff has been mailed; contain a brief description of the kinds of services to be furnished at the rates specified therein; and summarize the circumstances which show that all requisite agreement to the rate schedule or tariff or the filing thereof, including any contract embodied therein, has in fact been obtained. In the case of coordination and interchange arrangements in the nature of power pooling transactions, all supporting data required to be submitted in support of a rate schedule or tariff filing shall also be submitted by parties filing certificates of concurrence, or a representative to file supporting data on behalf of all parties may be designated as provided in § 35.1.
  • (a) Every public utility shall file the information required by this section, as applicable, at the time it files with the Commission under § 35.1 all or part of a rate schedule, tariff or service agreement to supersede or otherwise change the provisions of a rate schedule, tariff or service agreement filed with the Commission under § 35.1. Any petition filed under § 385.207 of this chapter for waiver of any provision of this section shall specifically identify the requirement that the applicant wishes the Commission to waive.
    (1) Except as provided in paragraph (a)(2) of this section, any utility that files a rate schedule, tariff, or service agreement change shall submit with its filing the information specified in paragraphs (b), (c), (d), (e), and (h) of this section, in accordance with paragraph (g) of this section.
    (i) Any utility that files a rate increase for power or transmission services not covered by paragraph (a)(2)(ii) of this section may elect to file under this paragraph instead of paragraph (a)(1) of this section, if the proposed increase for the Test Period, as defined in paragraph (a)(2)(i)(A) of this section, is equal to or less than $200,000, regardless of customer consent, or equal to or less than $1 million if all wholesale customers that belong to the affected rate class consent.
    (A) The Test Period, for purposes of paragraph (a)(2)(i) of this section, means the most recent calendar year for which actual data are available, the last day of which is no more than fifteen months before the date of tender for filing under § 35.1 of the notice of rate schedule.
    (B) Any utility that elects to file under this subparagraph must file the following information, conforming its submission to any rule of general applicability and to any Commission order specifically applicable to such utility:
    (1) A complete cost of service analysis for the Test Period, consistent with the requirements of paragraph (h)(36), Statement BK, of this section.
    (2) A complete derivation and explanation of all allocation factors and special assignments, consistent with the information required in § 35.12(b)(5).
    (3) A complete calculation of revenues for the Test Period and for the first 12 months after the proposed effective date, consistent with the requirements of paragraph (c)(1) of this section.
    (4) If the proposed rates contain a fuel cost or purchased economic power adjustment clause, as defined in § 35.14, the company must provide the derivation of its base cost of fuel (Fb) and its monthly fuel factors (Fm) for the Test Period and the resulting fuel adjustment clause revenues. If any pro forma adjustments affect the fuel clause in any way, the company must show the impact on Fm, kWh sales in the base period (Sm), Fb and kWh sales in the current period (Sb), as well as on fuel adjustment clause revenues.
    (5) Rate design calculations and narrative consistent with the information required in paragraph (h)(37) of this section and in § 35.12(b)(5).
    (6) The information required in paragraphs (b), (c)(2) and (c)(3) of this section and in § 35.12(b)(2).
    (C) Data shall be reconciled with the utility's most recent FERC Form 1. If the utility has not yet submitted Form 1 for the Test Period, the utility shall submit the relevant Form 1 pages in draft form.
    (D) The utility may make pro forma adjustments for post-Test Period changes that occur before the proposed effective date and that are known and measurable at the time of filing. The utility shall provide a narrative statement explaining all pro forma adjustments.
    (E) If the utility models its filing in whole or in part on retail rate decisions or settlements, the utility must provide detailed calculations and a narrative statement showing how all retail rate treatments are factored into the cost of service.
    (F) If the Commission sets the filing for hearing, the Commission will allow the company a specific time period in which to file testimony, exhibits, and supplemental workpapers to complete its case-in-chief. While not required under this subpart, a utility may elect to submit Statements AA through BM for the Test Period in accord with the requirements of paragraphs (d), (g) and (h) of this section.
    (ii) Any utility that files a rate increase for any service of short duration and of a type for which the need and usage cannot be reasonably forecasted (such as emergency or short-term power), or for service that is an integral part of a coordination and interchange arrangement, may submit with its filing only the information required in paragraphs (b), (c) and (h)(37) of this section and in § 35.12(b)(2) and (b)(5), conforming its submission to any rule of general applicability and to any Commission order specifically applicable to such utility.
    (iii) Any utility that files a rate change that does not provide for a rate increase or that provides for a rate increase that is based solely on a change in delivery points, a change in delivery voltage, or a similar change in service, must submit with its filing only the information required in paragraphs (b) and (c) of this section.
    (iv) For purposes of this subparagraph and paragraph (d)(2)(ii) of this section, the amount of any rate increase shall be the difference between the total revenues to be recovered under the rate change and the total revenues recovered or recoverable under the rate to be superseded or supplemented and shall be determined by:
    (A) applying the components of the rate to be superseded or supplemented to the billing determinants for the twelve months of Period I;
    (B) Applying the components of the rate change to the billing determinants for the twelve months of Period I; and
    (3) The Director of the Office of Energy Market Regulation may, by letter, require a utility that is not required under paragraph (a)(1) of this section to submit cost of service data to submit such specified cost of service data as are needed for Commission analysis of the rate schedule change.
  • Upon further order of this Commission issued upon its own motion or upon complaint or request by any person or State within the meaning of sections 19 or 20 of the Federal Power Act, the provisions of §§ 35.1 through 35.19 shall be operative as to any licensee or others who are subject to this Commission's jurisdiction in respect to services and the rates and charges of payment therefor by reason of the requirements of sections 19 or 20 of the Federal Power Act. The requirement of this section for compliance with the provisions of §§ 35.1 through 35.19 shall be in addition to and independent of any obligation for compliance with those regulations by reason of the provisions of sections 205 and 206 of the Federal Power Act. For purposes of applying this section Electric Service as otherwise defined in § 35.2(a) shall mean: Services to customers or consumers of power within the meaning of sections 19 or 20 of the Federal Power Act which may be comprised of various classes of capacity and energy and/or transmission services subject to the jurisdiction of this Commission. Electric Service shall include the utilization of facilities owned or operated by any licensee or others to effect any of the foregoing sales or services whether by leasing or other arrangements. As defined herein Electric Service is without regard to the form of payment or compensation for the sales or services rendered, whether by purchase and sale, interchange, exchange, wheeling charge, facilities charge, rental or otherwise. For purposes of applying this section, Rate Schedule as otherwise defined in § 35.2(b) shall mean: A statement of
  • (See §§ 35.1 through 35.21 of this chapter.)

Citations to §35.1(a)

Citations to §35.1(g)

  • (a) Every public utility shall file with the Commission and post, in conformity with the requirements of this part, full and complete rate schedules and tariffs and those service agreements not meeting the requirements of § 35.1(g), clearly and specifically setting forth all rates and charges for any transmission or sale of electric energy subject to the jurisdiction of this Commission, the classifications, practices, rules and regulations affecting such rates, charges, classifications, services, rules, regulations or practices, as required by section 205(c) of the Federal Power Act (49 Stat. 851; 16 U.S.C. 824d(c)). Where two or more public utilities are parties to the same rate schedule or tariff, each public utility transmitting or selling electric energy subject to the jurisdiction of this Commission shall post and file such rate schedule, or the rate schedule may be filed by one such public utility and all other parties having an obligation to file may post and file a certificate of concurrence on the form indicated in § 131.52 of this chapter: Provided, however, In cases where two or more public utilities are required to file rate schedules or certificates of concurrence such public utilities may authorize a designated representative to file upon behalf of all parties if upon written request such parties have been granted Commission authorization therefor.