§292.201. Scope.
18 C.F.R. § 292.201
This subpart applies to the criteria for and manner of becoming a qualifying small power production facility and a qualifying cogeneration facility under sections 3(17)(C) and 3(18)(B), respectively, of the Federal Power Act, as amended by section 201 of the Public Utility Regulatory Policies Act of 1978 (PURPA).
Notes, amendments, and revision history
Amendments
[45 FR 17972, Mar. 20, 1980]
Authority
Authority: Public Utility Regulatory Policies Act of 1978, (16 U.S.C. 2601, et seq. ), Energy Supply and Environmental Coordination Act, (15 U.S.C. 791 et seq. ), Federal Power Act, as amended, (16 U.S.C. 792, et seq. ), Department of Energy Organization Act, (42 U.S.C. 7101 et seq. ), E.O. 12009, 42 FR 46267, Natural Gas Policy Act of 1978, (15 U.S.C. 3301, et seq. ).
Authority
Authority: 16 U.S.C. 791a-825r, 2601-2645; 31 U.S.C. 9701; 42 U.S.C. 7101-7352.
Amendments
[45 FR 17972, Mar. 20, 1980]