§12.3. Definitions. — Inbound Citations

18 C.F.R. § 12.3

Cited by 9 regulations in release Current.

Citations to §12.3(b)(4)

  • (1) An applicant or licensee must report by email or telephone to the Regional Engineer any condition affecting the safety of a project or projects works, as defined in § 12.3(b)(4). The initial report must be made as soon as practicable after that condition is discovered, preferably within 72 hours, without unduly interfering with any necessary or appropriate emergency repair, alarm, or other emergency action procedure.
  • (b) The licensee must provide that if, in the course of a periodic inspection or comprehensive assessment conducted under this subpart D, an independent consultant discovers any condition for which emergency corrective measures are advisable, such as a condition affecting the safety of a project or project works as defined in § 12.3(b)(4) of this part, the independent consultant must immediately notify the licensee and the licensee must report that condition to the Regional Engineer pursuant to § 12.10(a) of this part. Emergency corrective measures must be included in the corrective plan and schedule required by paragraph (a)(1) of this section, and are also subject to paragraphs (a)(2) and (a)(3) of this section.

Citations to §12.3(b)(9)

  • (2) Designed to provide early warning to upstream and downstream inhabitants, property owners, operators of water-related facilities, recreational users, and other persons in the vicinity who might be affected by a project emergency as defined in § 12.3(b)(9).

Citations to §12.3(b)(13)(i)

  • (b) Has a project work (dam or water conveyance) or any portion thereof that has a high hazard potential, as defined in § 12.3(b)(13)(i); or
  • The licensee of any dam or other project work classified as having a high or significant hazard potential, as defined in § 12.3(b)(13)(i) and (ii), is required to submit an Owner's Dam Safety Program to the Regional Engineer.
  • (a) The Owner's Dam Safety Program shall designate either a Chief Dam Safety Engineer or Chief Dam Safety Coordinator, as defined in § 12.61. Any Owner's Dam Safety Program that includes one or more dams or other project works classified as having a high hazard potential, as defined in § 12.3(b)(13)(i), shall designate a Chief Dam Safety Engineer.
  • (a) For licensees of one or more dams or other project works classified as having a high hazard potential, as defined in § 12.3(b)(13)(i), an independent external audit or peer review of the Owner's Dam Safety Program, and the implementation thereof, shall be performed at an interval not to exceed five years.

Citations to §12.3(b)(13)(ii)

Citations to §12.3(b)(13)(iii)