§152.109. Project eligibility: Airport planning.
14 C.F.R. § 152.109
Airport master planning. A proposed project for airport master planning is not approved unless—
The location of the existing or proposed airport is included in the current NASP;
In the opinion of the Administrator, the proposed planning would promote the effective location of public airports and the development of an adequate NASP;
The project is airport master planning as defined in § 152.3;
If the project has been determined to have areawide significance by an appropriate areawide agency, it has been incorporated into a unified planning work program; and
In the case of a proposed project for airport master planning in a large or medium air traffic hub, in the opinion of the Administrator—
There is an appropriate system plan identifying the need for the airport;
The absence of a system plan is due to the failure of the responsible planning agency to proceed with its preparation; or
An existing system plan is not acceptable.
Airport system planning. A proposed project for airport system planning is not approved unless—
In the opinion of the Administrator, the project promotes the effective location of public airports;
In the opinion of the Administrator, the project promotes the development of an adequate NASP;
The project is airport system planning as defined in § 152.3; and
When the project encompasses a metropolitan area that includes a large or medium hub airport, the project is incorporated in a unified planning work program.
Notes, amendments, and revision history
Source
Source: Docket 19430, 45 FR 34786, May 22, 1980, unless otherwise noted.
Authority
Authority: 49 U.S.C. 106(g), 47106, 47127.
Source
Source: Docket 19430, 45 FR 34784, May 22, 1980, unless otherwise noted.