§900.8. IIP Process review meeting. — Inbound Citations
10 C.F.R. § 900.8
Statutory Authority
Cited by 4 regulations in release Current.
Citations to 10 U.S.C. § 900.8 as a whole
-
-
(d) the initial meeting, review meeting, and close-out meeting. These meetings, defined in §§ 900.5, 900.8 and 900.9, are milestones in the process and do not preclude any additional meetings or communications between the project proponent and the relevant Federal entities. The iterative nature of the process is provided for in procedures for evaluating the completeness of submitted materials and the suitability of materials for the relevant Federal entities' decision-making before each milestone.
-
(a) The project proponent shall prepare and submit to DOE the 13 project proponent resource reports described in this section. The project proponent may submit the resource reports at any time before requesting a review meeting under § 900.8 and shall, at the direction of DOE, revise resource reports in response to comments received from relevant Federal entities and relevant non-Federal entities during the Integrated Interagency Pre-Application (IIP) Process.
-
(a) An Integrated Interagency Pre-Application (IIP) Process close-out meeting concludes the IIP Process for a proposed electric transmission project and may only be held after the project proponent submits a close-out meeting request to DOE. The project proponent may submit the request at any time following the submission of the updated resource reports as required under § 900.8. The close-out meeting request shall include:(1) A summary table of changes made to the proposed project during the IIP Process, including potential environmental and community benefits from improved siting or design;(2) A description of all changes made to the proposed project since the review meeting, including a summary of changes made to the updated resource reports in response to the concerns raised during the review meeting;(3) A final public engagement plan, as described in § 900.5(d)(2);(4) Requests for Federal authorizations for the proposed project; and(5) An updated estimated timeline of filing requests for all other authorizations and consultations with non-Federal entities.