§429.73. Department of Energy recognition of nationally recognized certification programs for electric motors, including dedicated-purpose pool pump motors. — Inbound Citations
10 C.F.R. § 429.73
Statutory Authority
Cited by 7 regulations in release Current.
Citations to 10 U.S.C. § 429.73 as a whole
-
-
(i) A manufacturer may have a certification program, that DOE has classified as nationally recognized under § 429.73, certify the nominal full-load efficiency of a basic model of electric motor, and issue a certificate of conformity for the motor.
-
(2) Testing was conducted using a laboratory other than an accredited laboratory that meets the requirements of paragraph (d) of this section, or the full-load efficiency of the dedicated-purpose pool pump motor basic model was determined through the application of an AEDM pursuant to the requirements of § 429.70(k), and a third-party certification organization that is nationally recognized in the United States under § 429.73 has certified the full-load efficiency of the dedicated-purpose pool pump motor basic model through issuance of a certificate of conformity for the basic model.
-
(B) Have a certification body recognized under § 429.73 certify the results of the AEDM as accurately representing the basic model's average full-load efficiency. The simulated full-load efficiency for each basic model must be greater than or equal to 90 percent of the certified full-load losses (i.e., 0.90 × certified full-load losses ≤ simulated full-load losses).
-
(1) If DOE believes that an accreditation body or certification program that has been recognized under § 429.73 or § 429.74, respectively, is failing to meet the criteria of paragraph (b) of the section under which it is recognized, or if the certification program fails to meet the provisions at § 429.73(e), the Department will issue a Notice of Withdrawal (“Notice”) to inform such entity and request that it take appropriate corrective action(s) specified in the Notice. The Department will give the entity an opportunity to respond. In no case shall the time allowed for corrective action exceed 180 days from the date of the notice (inclusive of the 30 days allowed for disputing the bases for DOE's notification of withdrawal). If the entity wishes to dispute any bases identified in the Notice, the entity must respond to DOE within 30 days of receipt of the Notice. If after receiving such response, or no response, the Department believes satisfactory correction has not been made, the Department will withdraw its recognition from that entity.
Citations to §429.73(a)
-
(a) Any petition submitted to the Department pursuant to § 429.73(a) or § 429.74(a), shall be entitled “Petition for Recognition” (“Petition”) and must be submitted to the Department of Energy, Office of Energy Efficiency and Renewable Energy, Building Technologies Office, Appliance and Equipment Standards Program, EE-5B, 1000 Independence Avenue SW, Washington, DC 20585-0121, or via email (preferred submittal method) to [email protected]. In accordance with the provisions set forth in 10 CFR 1004.11, any request for confidential treatment of any information contained in such a Petition or in supporting documentation must be accompanied by a copy of the Petition or supporting documentation from which the information claimed to be confidential has been deleted.
Citations to §429.73(e)
-
(1) If DOE believes that an accreditation body or certification program that has been recognized under § 429.73 or § 429.74, respectively, is failing to meet the criteria of paragraph (b) of the section under which it is recognized, or if the certification program fails to meet the provisions at § 429.73(e), the Department will issue a Notice of Withdrawal (“Notice”) to inform such entity and request that it take appropriate corrective action(s) specified in the Notice. The Department will give the entity an opportunity to respond. In no case shall the time allowed for corrective action exceed 180 days from the date of the notice (inclusive of the 30 days allowed for disputing the bases for DOE's notification of withdrawal). If the entity wishes to dispute any bases identified in the Notice, the entity must respond to DOE within 30 days of receipt of the Notice. If after receiving such response, or no response, the Department believes satisfactory correction has not been made, the Department will withdraw its recognition from that entity.