Fair Licensing for Operations of Water Structures Act
A BILL
To amend the Federal Power Act to address certain alterations in, and the maintenance and repair of, project works, to provide for the licensing of micro hydrokinetic energy projects, and for other purposes.
Sec. 2 Hydropower maintenance and temporary adjustments
Sec. 3 Micro hydrokinetic energy projects
“37. Licensing of micro hydrokinetic energy projects
“(a) Definition of micro hydrokinetic energy project—In this section, the term micro hydrokinetic energy project—
“(1) means a project that—
“(A) has or will have an installed capacity of not more than 5 megawatts; and
“(B) converts to electric energy the hydrokinetic energy from a generator driven by a turbine from—
“(i) waves, tides, or currents in oceans, estuaries, or tidal areas; or
“(ii) free flowing water in rivers, lakes, streams, or man-made channels; and
“(2) does not include a project that impounds water to generate electricity.
“(b) Authorization—The Commission may issue a license in accordance with this section for a term of not less than 10, and not more than 20, years for the construction, operation, and maintenance of project works for a micro hydrokinetic energy project.
“(c) Expedited licensing process
“(1) Notification of intent
“(A) Filing of notification—An applicant for a license under this section shall commence the licensing process by filing a notification of intent with the Commission.
“(B) Existing license deadline—Notwithstanding section 15(b)(1), an applicant for a license under this section shall file a notification of intent under subparagraph (A) not later than 2 years before the expiration of an existing license, if applicable.
“(2) Filing of application
“(A) In general—Except as provided in subparagraph (B), an applicant for a license under this section shall submit to the Commission an application not later than 1 year after the date on which the applicant files a notification of intent under paragraph (1).
“(B) Existing license deadline—Notwithstanding section 15(c)(1), an applicant for a license under this section shall file an application with the Commission not later than 1 year before the date of expiration of the term of an existing license, if applicable.
“(3) Deadline for issuance—The Commission shall take final action on an application for a license under this section not later than 1 year after the date on which the application is filed under paragraph (2).
“(4) Schedule for final action—To the extent reasonably practicable, the Commission and any applicable conditioning or permitting agencies shall establish, with respect to each micro hydrokinetic energy project that is the subject of a notification of intent to apply for a license under this section, a joint schedule that permits the timely completion of decisions required to be made with respect to, and the timely issuance of, authorizations required under Federal law by the Commission and the conditioning or permitting agencies, subject to the requirement that any joint schedule established under this paragraph shall comply with the deadline for final action established under paragraph (3).
“(d) Regulations
“(1) In general—Not later than 180 days after the date of enactment of this section, the Commission shall promulgate regulations to implement this section in a manner that expedites the deployment of micro hydrokinetic energy projects while ensuring the safe operation of the micro hydrokinetic energy project in compliance with applicable Federal and State laws.
“(2) Inclusion—The regulations promulgated under paragraph (1) shall provide for the use of 1 or more categorical exclusions, including allowing for extraordinary circumstances under which the categorical exclusion shall not be available, under the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.) for low disturbance activities necessary for micro hydrokinetic energy projects.
“(e) Report to congress—The Commission shall submit to Congress a report describing the impacts of the micro hydrokinetic energy projects licensed under this section on the environment, the economy, and the reliability and affordability of electricity not later than the earlier of—
“(1) the date that is 5 years after the date of enactment of this section; and
“(2) the date on which the first 50 micro hydrokinetic energy projects licensed under this section have been operational for not less than 1 year.
“(f) Savings clause—Nothing in this section affects any authority of the Commission, at the election of an applicant, to license the construction, operation, and maintenance of project works for a micro hydrokinetic energy project under any other provision of this part.”