Contemporaneous Land and Environmental Action for Neutralizing Unreclaimed Property at Mines Act of 2026
A BILL
To amend the Surface Mining Control and Reclamation Act of 1977 to strengthen control of the environmental impacts of surface coal mining, and for other purposes.
Sec. 2 Amendments to Surface Mining Control and Reclamation Act of 1977
“(3) A request to temporarily cease or suspend mining operations is a significant permit revision for purposes of paragraph (2).
“(4) In each case where no active coal removal or reclamation has occurred at a permitted mine for more than 6 months during any 3-year period, the applicable permit shall be considered out of compliance with the reclamation plan—
“(A) unless the permit is in compliance with the standards established in section 515(b)(3) and does not have any variances from such standards; and
“(B) until the date on which the regulatory authority approves—
“(i) a reasonable plan submitted by the operator to return to production not later than 1 year after the date on which the operator is notified that the applicable permit is considered out of compliance under this paragraph; or
“(ii) an application for a revision of the permit submitted by the permittee under paragraph (1).”
“(C) in no instance shall the operator be allowed more than 1 year greater than the time periods set forth in this subsection to achieve successful revegetation;”
“(7) All backfilling and regrading to ensure proper drainage control, prevent leaching of toxic materials, eliminate highwalls, spoil piles, and depressions (unless small depressions are needed in order to retain moisture to assist revegetation or as otherwise authorized pursuant to this Act), and ensure stability, shall be completed not later than 180 days after the date of coal production as reported pursuant to section 402(c).”
“(2) the regulatory authority shall—
“(A) require quarterly monitoring of both surface water and ground water during mining and reclamation;
“(B) specify those—
“(i) monitoring sites to record the quantity and quality of surface drainage above and below the mine site as well as in the potential zone of influence;
“(ii) monitoring sites to record level, amount, and samples of ground water and aquifers potentially affected by the mining and also directly below the lowermost (deepest) coal seam to be mined;
“(iii) records of well logs and borehole data to be maintained; and
“(iv) monitoring sites to record precipitation; and
“(C) require the monitoring, data collection, and analysis required by this section to be conducted according to standards and procedures set forth by the regulatory authority in order to ensure their reliability and validity;”
“(3) the regulatory authority shall conduct an annual assessment of the biological condition of streams to demonstrate progress with respect to restoring of the pre-mining biological condition of the stream;
“(4) the regulatory authority shall conduct an inspection of surface water runoff control structures after each precipitation event that is at least as intense as a 100-year, 6-hour precipitation event; and”