Build More Power Act
A BILL
To amend the Energy Policy Act of 2005 to extend the period of availability of funds and commitment authority for energy infrastructure reinvestment financing and to require the solicitation of applications from energy infrastructure required to generate electric energy during an emergency, and for other purposes.
Sec. 2 Loan guarantees for electric generating facilities required to operate per an emergency designation
“(g) Section 202(c) facilities
“(1) Treatment of required electric energy generation—Energy infrastructure that is required by an order issued under section 202(c) of the Federal Power Act to generate electric energy shall be considered to have ceased operations for purposes of subsection (a)(1).
“(2) Solicitation of applications
“(A) In general—If the Secretary issues an order under section 202(c) of the Federal Power Act requiring energy infrastructure to generate electric energy, the Secretary shall, when issuing such order, solicit an application for a guarantee under this section for a project described in paragraph (1), (2), or (3) of subsection (a) with respect to such energy infrastructure.
“(B) Existing orders—With respect to any energy infrastructure required to generate electric energy by an order issued under section 202(c) of the Federal Power Act on or before the date of enactment of this subsection, and if such order is in effect on such date of enactment, the Secretary shall, not later than 60 days after such date of enactment, solicit applications for a guarantee under this section for projects described in paragraph (1), (2), or (3) of subsection (a) with respect to such energy infrastructure.”
“(1) In general—The Secretary may”
“(2) Set aside for certain section 202(c) facilities—Of the total principal amount described in paragraph (1), not less than $20,000,000,000 of such amount shall be used to guarantee loans for projects described in section 1706(a) of the Energy Policy Act of 2005 with respect to energy infrastructure required to generate electric energy by an order issued under section 202(c) of the Federal Power Act.”