Stopping Hikes In Electricity from Large Load Demands Act
A BILL
To amend the Public Utility Regulatory Policies Act of 1978 to add a standard relating to the consideration of large load facilities as a class of electric consumers, and for other purposes.
Sec. 2 PURPA standards for large load facilities
“(22) Large load facility class
“(A) Classification—Large load facilities shall be considered a class of electric consumers.
“(B) Cost recovery relating to large load facility class—Each electric utility that provides electric service to a class of electric consumers described in subparagraph (A) shall fully recover from such class all costs associated with any upgrade made to the generation, transmission, or distribution facilities of the electric grid, including local facilities, in order to meet the demand for electric energy from such class, including in the event that a large load facility ceases operations or uses less electric energy than projected at the time of such upgrade.
“(23) Grid reliability for large load facilities—Each electric utility shall prioritize, among requests from owners or operators of large load facilities for electric service, such a request under which the owner or operator agrees to employ—
“(A) features that reduce the demand for electric energy from the electric grid during times of peak demand, including—
“(i) energy efficiency or energy conservation measures;
“(ii) onsite energy storage; or
“(iii) demand response or load flexibility technologies; and
“(B) zero-emission electric energy generated onsite or procured within the same balancing authority through a power purchase agreement to meet all of the demand of the large load facility for electric energy.”
“(e) Definitions—For the purposes of subsection (d):
“(1) Large load facility—The term large load facility—
“(A) means a facility, or an aggregation of facilities at a single site, with respect to which the peak demand of such facility or such aggregation of facilities exceeds 75 megawatts; and
“(B) does not include an existing facility with respect to which any increased demand is predominantly caused by electrification or measures to reduce greenhouse gas emissions.
“(2) Zero-emission electric energy—The term zero-emission electric energy means electric energy generated without emitting greenhouse gases, including from solar, wind, geothermal, hydroelectric, tidal, fission, or fusion.”
“(9)
“(A) Not later than 1 year after the date of enactment of this paragraph, each State regulatory authority (with respect to each electric utility for which the State has ratemaking authority) and each nonregulated utility shall commence consideration under section 111, or set a hearing date for consideration, with respect to each standard established by paragraphs (22) and (23) of section 111(d).
“(B) Not later than 2 years after the date of enactment of this paragraph, each State regulatory authority (with respect to each electric utility for which the State has ratemaking authority), and each nonregulated electric utility shall complete the consideration and make the determination under section 111 with respect to each standard established by paragraphs (22) and (23) of section 111(d).
“(C) Not later than 30 days after completing the consideration and making a determination under section 111 with respect to each standard established by paragraphs (22) and (23) of section 111(d), each State regulatory authority (with respect to each electric utility for which the State has ratemaking authority), and each nonregulated electric utility shall submit to the Committee on Energy and Commerce of the House of Representatives and the Committee on Energy and Natural Resources of the Senate a report detailing the process used for consideration and an explanation for the determination.”
“(i) Other prior State actions—Subsections (b) and (c) shall not apply to the standards established by paragraphs (22) and (23) of section 111(d) in the case of any electric utility in a State if, before the date of enactment of this subsection—
“(1) the State has implemented for the electric utility the standard concerned (or a comparable standard);
“(2) the State regulatory authority for the State or the relevant nonregulated electric utility has conducted a proceeding to consider implementation of the standard concerned (or a comparable standard) for the electric utility; or
“(3) the State legislature has voted on the implementation of the standard concerned (or a comparable standard) for the electric utility during the 3-year period ending on that date of enactment.”