(i)
a plan for conducting such feasibility study, including a plan—
(I)
to conduct an analysis of—
(aa)
the demand for electricity in the region of the proposed site of the advanced nuclear reactor and supporting facilities;
(bb)
the transmission capacity and transmission facilities and systems in such region; and
(cc)
the structure of the market for electricity in such region;
(II)
to conduct an analysis of how the construction and operation of the advanced nuclear reactor at such proposed site would impact—
(aa)
the overall demand for electricity in such region;
(bb)
the transmission capacity and transmission facilities and systems in such region; and
(cc)
the market for electricity in such region;
(III)
to conduct an analysis regarding the proposed site of the advanced nuclear reactor and supporting facilities, including preliminary site layout and site preparation and potential effects of the advanced nuclear reactor and supporting facilities on the applicable region, including population distribution and the current uses of land and water;
(IV)
to conduct an analysis of the environmental impacts of siting, construction, and operation of the advanced nuclear reactor at the proposed site, including—
(aa)
a comparison of the environmental impacts of siting, constructing, and operating the advanced nuclear reactor at such proposed site to siting, constructing, and operating the advanced nuclear reactor at other sites with similar characteristics in the applicable region;
(bb)
impacts on cooling water demand; and
(cc)
an overview of the environmental protection requirements in the applicable region;
(V)
for how to approach the licensing process and authorization requirements for the siting, construction, and operation of the advanced nuclear reactor;
(VI)
to conduct an analysis of how the applicable project to site, construct, and operate the advanced nuclear reactor would be implemented, including analysis of potential contractual approaches, procurement plans, project schedules, project management, and risk management plans;
(VII)
to conduct an analysis of organizational requirements and responsibilities for each phase of the applicable project to site, construct, and operate the advanced nuclear reactor, including requirements and responsibilities relating to human resources and training, including workforce logistics and staffing requirements for construction, commissioning, operation, and maintenance of the advanced nuclear reactor, including education and other training requirements;
(VIII)
to conduct an analysis of the economic feasibility of the applicable project to site, construct, and operate the advanced nuclear reactor, including a cost-benefit analysis;
(IX)
for developing plans for emergency preparedness and coordination for the proposed site of the advanced nuclear reactor and supporting facilities, including on-site emergency planning and coordination with off-site emergency response organizations;
(X)
to conduct an analysis of cogeneration opportunities on the proposed site of the advanced nuclear reactor and supporting facilities; and
(XI)
to conduct a decommissioning analysis for the advanced nuclear reactor, including the cost of decommissioning the advanced nuclear reactor, decommissioning phases for the advanced nuclear reactor, and the environmental impact of decommissioning the advanced nuclear reactor; and