(a)
In general— The Chairman of the Nuclear Regulatory Commission shall assign, for the duration described in subsection (b), a resident inspector to each commercial nuclear power plant that has permanently ceased operation to conduct inspections of decommissioning activities and spent nuclear fuel transfer activities of the commercial nuclear power plant.
(b)
Duration described— The duration described in this subsection is the period of time it takes to transfer all spent nuclear fuel from the spent fuel pools of the commercial nuclear power plant.
(c)
Reassignment— If there are no decommissioning activities or spent nuclear fuel transfer activities at the commercial nuclear power plant to which a resident inspector is assigned under subsection (a), the Chairman of the Nuclear Regulatory Commission may assign such resident inspector to a different commercial nuclear power plant.