Improving Embassy Design and Security Act
A BILL
To improve the design and construction of diplomatic posts, and for other purposes.
2. Standardization in capital construction
3. Statement of policy
4. Capital construction transparency
“(a) In general—Not later than 180 days after the date of the enactment of this subsection, and every 90 days thereafter until September 30, 2023, the Secretary shall submit to the appropriate congressional committees a comprehensive report regarding all ongoing overseas capital construction projects and major embassy security upgrade projects.
“(b) Contents—Each report required under subsection (a) shall include the following with respect to each ongoing overseas capital construction project and major embassy security upgrade project:
“(1) The initial cost estimate as specified in the proposed allocation of capital construction and maintenance funds required by the Committees on Appropriations for Acts making appropriations for the Department of State, foreign operations, and related programs.
“(2) The current cost estimate.
“(3) The value of each request for equitable adjustment received by the Department of State to date.
“(4) The value of each certified claim received by the Department of State to date.
“(5) The value of any usage of the project’s contingency fund to date and the value of the remainder of the project’s contingency fund.
“(6) An enumerated list of each request for adjustment and certified claim that remains outstanding or unresolved.
“(7) An enumerated list of each request for equitable adjustment and certified claim that has been fully adjudicated or that the Department has settled, and the final dollar amount of each adjudication or settlement.
“(8) The date of estimated completion specified in the proposed allocation of capital construction and maintenance funds required by the Committees on Appropriations not later than 45 days after the date of the enactment of an Act making appropriations for the Department of State, foreign operations, and related programs.
“(9) The current date of estimated completion.”