Next Generation Grid Resources and Infrastructure Development Act
A BILL
To amend the Public Utility Regulatory Policies Act of 1978 to provide for the integration of distributed energy resources, to modernize electricity grid infrastructure, to provide for the consideration of non-wires alternatives, and for other purposes.
Sec. 2 General right of interconnection
“5. General right of interconnection
“(a) Definition of distributed energy resource—In this section, the term distributed energy resource means a resource, technology, or combination of resources and technologies interconnected to the electricity distribution system that generates, manages, or reduces energy use.
“(b) Right of interconnection—Distributed energy resources shall have a general right of interconnection under this Act.
“(c) Analysis of interconnection requests—The methods used to calculate the impacts of proposed interconnections under this Act shall be transparent, repeatable, consistent, clearly established, and agreed to by the appropriate State regulatory authority.
“(d) Rates and fees—As the State or appropriate State regulatory authority determines to be appropriate, each electric utility shall adopt standards, conditions, and requirements for rates and fees for the interconnection of distributed energy resources under this Act, that—
“(1) reflect the 2-way costs and benefits for the distributed energy resource and the electricity grid;
“(2) provide fair credit for energy exported to the electricity grid;
“(3) are transparently derived and consistently applied; and
“(4) are not punitive.
“(e) Timeframes
“(1) In general—Timeframes for the interconnection of distributed energy resources under this Act shall be well-defined, expeditious, and not unduly protracted, as determined by the appropriate State regulatory authority.
“(2) Delays or denial—An interconnection of distributed energy resources under this Act shall not be delayed or denied unless the electric utility demonstrates that—
“(A) the interconnection is unsafe or impracticable; and
“(B) any safety or impracticability issue demonstrated under subparagraph (A) cannot be mitigated.”
Sec. 3 Electricity distribution resource planning
“(20) Electricity distribution resource planning
“(A) Definitions—In this paragraph:
“(i) Distributed energy resource—The term distributed energy resource has the meaning given the term in section 5(a).
“(ii) Microgrid—The term microgrid means a group of interconnected loads and distributed energy resources within clearly defined electrical boundaries that—
“(I) acts as a single controllable entity with respect to the electricity grid; and
“(II) can connect and disconnect from the electricity grid to operate in grid-connected mode and island mode.
“(B) Requirement—Each electric utility shall develop an electricity distribution resource plan on a regular basis, as determined by the appropriate State regulatory authority.
“(C) Components of electricity distribution resource plan—An electricity distribution resource plan developed under subparagraph (B) shall identify—
“(i) the future electricity demand and distribution system requirements of the electric utility;
“(ii) projections for the deployment of distributed energy resources within the utility service territory during the period covered by the plan by size, type, and location;
“(iii) any locational benefits and costs of distributed energy resources to the distribution system of the electric utility and ratepayers, including—
“(I) benefits to grid resiliency and reliability;
“(II) avoided or incurred investments in distribution or transmission infrastructure;
“(III) avoided or incurred investments in generation capacity;
“(IV) any environmental benefits; and
“(V) any other costs or benefits to the electricity grid or to ratepayers;
“(iv) any temporal benefits or costs of distributed energy resources to the distribution system of the electric utility, including—
“(I) any changes in peak demand; and
“(II) any changes in the distribution load curve;
“(v) any investments needed to improve the integration, management, or deployment of distributed energy resources in the distribution system of the electric utility;
“(vi) any barriers to the integration of distributed energy resources in the distribution system of the electric utility, including limitations to system capacity that would require upgrades to integrate distributed energy resources;
“(vii) any locations on the distribution system of the electric utility suitable for microgrid development based on geographic, resiliency, reliability, or cost factors; and
“(viii) any physical and cybersecurity needs and vulnerabilities of the distribution system of the electric utility.
“(D) Designation of participants—For each electric utility for which the State or State regulatory authority has ratemaking authority, the State or State regulatory authority, as applicable, may designate participants to assist in developing an electricity distribution resource plan under subparagraph (B), including, as the State or State regulatory authority determines to be appropriate—
“(i) any nonprofit or for-profit entity with experience in planning, designing, or operating distributed energy resources or systems;
“(ii) a regional regulatory authority or other regional entity;
“(iii) an institution of higher education;
“(iv) a National Laboratory (as defined in section 2 of the Energy Policy Act of 2005 (42 U.S.C. 15801));
“(v) a ratepayer or advocate of ratepayers; and
“(vi) any other appropriate entity.
“(E) Access to data—In developing an electricity distribution resource plan under subparagraph (B), the electric utility shall provide to any participants designated under subparagraph (D) access to relevant data regarding the operation and performance of the electricity grid, subject to any qualifications and confidentiality requirements that the State regulatory authority determines to be appropriate.”
Sec. 4 Non-wires alternatives
“(30) Non-wires alternative—The term non-wires alternative means an electricity grid investment or project that uses one or more nontraditional solutions, including distributed generation, energy storage, energy efficiency, demand response, microgrids, or grid software and controls, to defer or replace the need for specific equipment upgrades or new infrastructure, such as transmission or distribution lines or transformers, at a substation or circuit level.”
“(h) Issuance of rule relating to consideration of non-Wires alternatives in regional transmission plans—As soon as practicable after the date of enactment of this subsection, the Commission shall issue a final rule that—
“(1) requires public utility transmission providers—
“(A) to solicit non-wires alternatives in the development of regional transmission plans; and
“(B) to identify opportunities for non-wires alternatives;
“(2) requires Transmission Organizations to develop procedures to control or manage non-wires alternatives providing transmission services; and
“(3) authorizes Transmission Organizations to allocate and recover costs of non-wires alternatives providing transmission services that are demonstrated to be a cost-effective alternative to an upgrade to, or the construction of new, transmission infrastructure in the same manner as the upgrade to, or construction of new, transmission infrastructure would have been allocated and recovered.”
“(21) Non-wires alternatives
“(A) In general—To the extent a State regulatory authority has the authority to allow electric utilities to recover costs associated with electricity transmission and distribution projects, each State regulatory authority shall consider non-wires alternatives (as defined in section 3 of the Federal Power Act (16 U.S.C. 796)) in instances in which an entity proposes transmission or distribution projects seeking cost-of-service rate recovery.
“(B) Cost recovery—To reduce the costs to ratepayers associated with potential upgrades to transmission or distribution infrastructure, the cost of a non-wires alternative considered under subparagraph (A) shall be recovered from ratepayers in the same manner as an upgrade to transmission or distribution infrastructure would have been.”
Sec. 5 Distribution system operator pilot program
Sec. 6 Consideration of performance-based incentive rates
“(22) Performance-based incentive mechanisms
“(A) In general—Each State regulatory authority, with respect to each electric utility for which the State regulatory authority has ratemaking authority, shall consider the use of performance-based incentive mechanisms to achieve public interest goals established by the State or State regulatory authority in accordance with subparagraphs (B) and (C).
“(B) Considerations for establishment of public interest goals—In establishing public interest goals under subparagraph (A), the State or State regulatory authority, as applicable, shall consider—
“(i) overall system efficiency, including reductions in peak demand;
“(ii) the integration and adoption of distributed energy resources;
“(iii) process improvements, such as predictable and timely interconnection processes;
“(iv) the resiliency and reliability of the electricity grid;
“(v) customer engagement and satisfaction;
“(vi) environmental benefits, including reductions in particulate and greenhouse gas emissions; and
“(vii) any other factor determined to be appropriate by the State or State regulatory authority.
“(C) Metrics—In establishing public interest goals under subparagraph (A), the State or State regulatory authority, as applicable, shall specify quantifiable metrics with respect to the public interest goals that can be measured and verified.”
“(7)
“(A) Not later than 1 year after the date of enactment of this paragraph, each State regulatory authority (with respect to each electric utility for which it has ratemaking authority) shall, with respect to the standards established by paragraphs (20) through (22) of section 111(d)—
“(i) commence the consideration referred to in section 111; or
“(ii) set a hearing date for the consideration.
“(B) Not later than 2 years after the date of enactment of this paragraph, each State regulatory authority (with respect to each electric utility for which it has ratemaking authority) shall—
“(i) complete the consideration required under subparagraph (A); and
“(ii) make the determination referred to in section 111 with respect to the standards established by paragraphs (20) through (22) of section 111(d).”
“(g) Prior state actions—Subsections (b) and (c) shall not apply to the standard established by paragraphs (20) through (22) of section 111(d) in the case of any electric utility in a State if, before the date of enactment of this subsection—
“(1) the State has implemented for the electric utility the standard (or a comparable standard);
“(2) the State regulatory authority for the State or the relevant nonregulated electric utility has conducted a proceeding to consider implementation of the standard (or a comparable standard) for the electric utility; or
“(3) the State legislature has voted on the implementation of the standard (or a comparable standard) for the electric utility.”