US Codex
Bill
Notes

H.R. 4568 — what changed

Enhancing Geothermal Production on Federal Lands Act

From Introduced in House to Reported in House. 2 sections amended between Introduced in House and Reported in House.

Sec. 2 Geothermal production on Federal lands

The Geothermal Steam Act of 1970 (30 U.S.C. 1001 et seq.) is amended by adding at the end the following:

“30. Geothermal exploration test projects

“(a) Definition of geothermal exploration test project—In this section, the term geothermal exploration test project means the drilling of a well to test or explore for geothermal resources on lands for which the Secretary has issued a lease under this Act, that—

“(1) is carried out by the holder of the lease;

“(2) causes—

“(A) less than 5 acres of soil or vegetation disruption at the location of each geothermal exploration well; and

“(B) not more than an additional 5 acres of soil or vegetation disruption during access or egress to the test site;

“(3) is developed—

changed “(A) 8 inches or less than 9 inches in diameter;

“(B) in a manner that does not require off-road motorized access other than to and from the well site along an identified off-road route;

changed “(C) without construction of new roads other than upgrading of existing drainage crossings for safety purposes; andpurposes;

changed “(D) with the use of rubber-tired digging or drilling equipment vehicles;vehicles; and

added “(E) without the use of high-pressure well stimulation;

“(4) is completed in less than 90 days, including the removal of any surface infrastructure from the site; and

“(5) requires the restoration of the project site within 3 years of the date of first exploration drilling to approximately the condition that existed at the time the project began, unless the site is subsequently used as part of energy development under the lease.

“(b) Categorical exclusion

“(1) In general—Unless extraordinary circumstances exist, a project that the Secretary determines under subsection (c) is a geothermal exploration test project shall be categorically excluded from the requirements for an environmental assessment or an environmental impact statement under the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.) or section 1508.4 of title 40, Code of Federal Regulations (or a successor regulation).

“(2) Extraordinary circumstances definition—In this subsection, the term “extraordinary circumstances” has the same meaning given such term in the Department of the Interior Departmental Manual, 516 DM 2.3A(3) and 516 DM 2, Appendix 2 (or successor provisions).

“(c) Process

“(1) Requirement to provide notice—A leaseholder shall provide notice to the Secretary of the leaseholder’s intent to carry out a geothermal exploration test project at least 30 days before the start of drilling under the project.

“(2) Review and determination—Not later than 10 days after receipt of a notice of intent under paragraph (1), the Secretary shall, with respect to the project described in the notice of intent—

“(A) determine if the project qualifies for a categorical exclusion under subsection (b); and

“(B) notify the leaseholder of such determination.

removed “(3) Opportunity to remedy

changed “(A) In general—If “(3) Opportunity to remedy—If the Secretary determines under paragraph (2)(A) that the project does not qualify for a categorical exclusion under subsection (b), the Secretary shall—

changed “(i) “(A) include in such notice clear and detailed findings on any deficiencies in the project that resulted in such determination; and

changed “(ii) “(B) allow the leaseholder to remedy any such deficiencies and resubmit the notice of intent under paragraph (1).”

Sec. 3 Geothermal leasing priority areas

The Geothermal Steam Act of 1970 (30 U.S.C. 1001 et seq.) is further amended by adding at the end the following:

“31. Geothermal leasing priority areas

“(a) Definition of covered land—In this section, the term “covered land” means land that is—

“(1) Federal land; and

“(2) not excluded from the development of geothermal energy under—

“(A) a land use plan established under the Federal Land Policy and Management Act of 1976 (43 U.S.C. 1701 et seq.); or

“(B) any other Federal law.

“(b) Designation of geothermal leasing priority areas—The Secretary, in consultation with the Secretary of Energy, shall designate portions of covered land as geothermal leasing priority areas as soon as practicable, but not later than 5 years, after the date of the enactment of this section.

“(c) Criteria for selection—In determining which covered lands to designate as geothermal leasing priority areas under subsection (b), the Secretary, in consultation with the Secretary of Energy, shall consider if—

“(1) the covered land is preferable for geothermal leasing;

“(2) production of geothermal energy on such land is economically viable, including if such land has access to methods of energy transmission; and

“(3) the designation would be in compliance with section 202 of the Federal Land Policy and Management Act of 1976 (43 U.S.C. 1712), including subsection (c)(9) of that section.

“(d) Review and modification—Not less frequently than once every 10 years, the Secretary shall—

“(1) review covered land and, if appropriate, make additional designations of geothermal leasing priority areas; and

“(2) review each area designated as a geothermal leasing priority area under this section, and, if appropriate, remove such designation.

“(e) Programmatic environmental impact statement

changed “(1) Initial designations—Not designations—No later than 5 years one year after the date of the enactment initial designation of this section, a geothermal leasing priority area, the Secretary shall prepare a supplement to any final programmatic environmental impact statement for geothermal leasing that is the most recently finalized such statement with respect to covered land designated as a geothermal leasing priority area under subsection (b).

“(2) Subsequent designations—Each designation of a geothermal leasing priority area under subsection (d) shall be included in a programmatic environmental impact statement for geothermal leasing or in a supplement to such a statement.

“(3) Consultations—In developing any programmatic environmental impact statement for geothermal leasing or supplement to such a statement under this section, the Secretary shall consult, on an ongoing basis, with appropriate State, Tribal, and local governments, transmission infrastructure owners and operators, developers, and other appropriate entities.

“(4) Procedure—The Secretary may not delay issuing a permit or holding a lease sale under this Act because the supplement required under paragraph (1) has not been finalized by the Secretary.

“(f) Compliance with NEPA—If the Secretary determines that the designation of a geothermal leasing priority area has been sufficiently analyzed by a programmatic environmental impact statement, the Secretary shall not prepare any additional analysis under the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.) with respect to geothermal lease sales for such geothermal leasing priority area.”