Section 1 Short title
This Act may be cited as the “HYdropower Permit Extension Act” or the “HYPE Act”.
AN ACT
To amend the Federal Power Act to provide for extended periods relating to preliminary permits and commencement of construction, and for other purposes.
“(1) extend the period of a preliminary permit once for not more than 4 additional years beyond the 4 years”
“(2) if the period of a preliminary permit is extended under paragraph (1), extend the period of such preliminary permit once for not more than 4 additional years beyond the extension period granted under paragraph (1), if the Commission determines that there are extraordinary circumstances that warrant such additional extension.”