§7607. Administrative proceedings and judicial review — Inbound Citations
42 U.S.C. § 7607
Cited by 22 provisions in release 119-102.
Citations to 42 U.S.C. § 7607 as a whole
-
(4) Notwithstanding section 7607 of this title, no action of the Administrator adding a pollutant to the list under subsection (b) or listing a source category or subcategory under subsection (c) shall be a final agency action subject to judicial review, except that any such action may be reviewed under such section 7607 of this title when the Administrator issues emission standards for such pollutant or category.
-
(7) The Administrator shall consider, but need not adopt, the recommendations contained in the report of the National Academy of Sciences prepared pursuant to this subsection and the views of the Science Advisory Board, with respect to such report. Prior to the promulgation of any standard under subsection (f), and after notice and opportunity for comment, the Administrator shall publish revised Guidelines for Carcinogenic Risk Assessment or a detailed explanation of the reasons that any recommendations contained in the report of the National Academy of Sciences will not be implemented. The publication of such revised Guidelines shall be a final Agency action for purposes of section 7607 of this title.
-
(1) Any standard under this section in effect before the date of enactment of the Clean Air Act Amendments of 1990 [November 15, 1990] shall remain in force and effect after such date unless modified as provided in this section before the date of enactment of such Amendments or under such Amendments. Except as provided in paragraph (4), any standard under this section which has been promulgated, but has not taken effect, before such date shall not be affected by such Amendments unless modified as provided in this section before such date or under such Amendments. Each such standard shall be reviewed and, if appropriate, revised, to comply with the requirements of subsection (d) within 10 years after the date of enactment of the Clean Air Act Amendments of 1990. If a timely petition for review of any such standard under section 7607 of this title is pending on such date of enactment, the standard shall be upheld if it complies with this section as in effect before that date. If any such standard is remanded to the Administrator, the Administrator may in the Administrator’s discretion apply either the requirements of this section, or those of this section as in effect before the date of enactment of the Clean Air Act Amendments of 1990.
-
(M) In addition to that described in subparagraph (L), the Board may use any information gathering authority of the Administrator under this chapter, including the subpoena power provided in section 7607(a)(1) of this title.
-
(O) After the effective date of any reporting requirement promulgated pursuant to subparagraph (C)(iii) it shall be unlawful for any person to fail to report any release of any extremely hazardous substance as required by such subparagraph. The Administrator is authorized to enforce any regulation or requirements established by the Board pursuant to subparagraph (C)(iii) using the authorities of sections 7413 and 7414 of this title. Any request for information from the owner or operator of a stationary source made by the Board or by the Administrator under this section shall be treated, for purposes of sections 7413, 7414, 7416, 7420, 7603, 7604 and 7607 of this title and any other enforcement provisions of this chapter, as a request made by the Administrator under section 7414 of this title and may be enforced by the Chairperson of the Board or by the Administrator as provided in such section.
-
(E) After the effective date of any regulation or requirement imposed under this subsection, it shall be unlawful for any person to operate any stationary source subject to such regulation or requirement in violation of such regulation or requirement. Each regulation or requirement under this subsection shall for purposes of sections 7413, 7414, 7416, 7420, 7604, and 7607 of this title and other enforcement provisions of this chapter, be treated as a standard in effect under subsection (d).
-
(3) For the purposes of sections 7410, 7604, and 7607 of this title, any order issued by the State and in effect pursuant to this subsection shall become part of the applicable implementation plan.
-
(e) Any action pursuant to this section, including any objection of the Administrator under the last sentence of subsection (b), shall be considered a final action for purposes of judicial review of any penalty under section 7607 of this title.
-
(4) For purposes of sections 7411(e), 7413, 7414, 7416, 7420, 7603, 7604, 7607 of this title and other provisions for the enforcement of this chapter, each performance standard, emission limitation or other requirement established pursuant to this section by the Administrator or a State or local government, shall be treated in the same manner as a standard of performance under section 7411 of this title which is an emission limitation.
-
(2) If the Administrator does not object in writing to the issuance of a permit pursuant to paragraph (1), any person may petition the Administrator within 60 days after the expiration of the 45-day review period specified in paragraph (1) to take such action. A copy of such petition shall be provided to the permitting authority and the applicant by the petitioner. The petition shall be based only on objections to the permit that were raised with reasonable specificity during the public comment period provided by the permitting agency (unless the petitioner demonstrates in the petition to the Administrator that it was impracticable to raise such objections within such period or unless the grounds for such objection arose after such period). The petition shall identify all such objections. If the permit has been issued by the permitting agency, such petition shall not postpone the effectiveness of the permit. The Administrator shall grant or deny such petition within 60 days after the petition is filed. The Administrator shall issue an objection within such period if the petitioner demonstrates to the Administrator that the permit is not in compliance with the requirements of this chapter, including the requirements of the applicable implementation plan. Any denial of such petition shall be subject to judicial review under section 7607 of this title. The Administrator shall include in regulations under this subchapter provisions to implement this paragraph. The Administrator may not delegate the requirements of this paragraph.
Citations to §7607(a)
-
(1) In determining the amount of any penalty to be assessed under this section or section 7604(a) of this title, the Administrator or the court, as appropriate, shall take into consideration (in addition to such other factors as justice may require) the size of the business, the economic impact of the penalty on the business, the violator’s full compliance history and good faith efforts to comply, the duration of the violation as established by any credible evidence (including evidence other than the applicable test method), payment by the violator of penalties previously assessed for the same violation, the economic benefit of noncompliance, and the seriousness of the violation. The court shall not assess penalties for noncompliance with administrative subpoenas under section 7607(a) of this title, or actions under section 7414 of this title, where the violator had sufficient cause to violate or fail or refuse to comply with such subpoena or action.
-
(B) In obtaining information under subparagraph (A), section 7607(a) of this title (relating to subpenas) shall be applicable.
Citations to §7607(b)
-
(c) A transport commission established under subsection (b) may request the Administrator to issue a finding under section 7410(k)(5) of this title that the implementation plan for one or more of the States in the transport region is substantially inadequate to meet the requirements of section 7410(a)(2)(D) of this title. The Administrator shall approve, disapprove, or partially approve and partially disapprove such a request within 18 months of its receipt and, to the extent the Administrator approves such request, issue the finding under section 7410(k)(5) of this title at the time of such approval. In acting on such request, the Administrator shall provide an opportunity for public participation and shall address each specific recommendation made by the commission. Approval or disapproval of such a request shall constitute final agency action within the meaning of section 7607(b) of this title.
-
(a) Except as provided in subsection (b), any person may commence a civil action on his own behalf—(1) against any person (including (i) the United States, and (ii) any other governmental instrumentality or agency to the extent permitted by the Eleventh Amendment to the Constitution) who is alleged to have violated (if there is evidence that the alleged violation has been repeated) or to be in violation of (A) an emission standard or limitation under this chapter or (B) an order issued by the Administrator or a State with respect to such a standard or limitation,(2) against the Administrator where there is alleged a failure of the Administrator to perform any act or duty under this chapter which is not discretionary with the Administrator, or(3) against any person who proposes to construct or constructs any new or modified major emitting facility without a permit required under part C of subchapter I (relating to significant deterioration of air quality) or part D of subchapter I (relating to nonattainment) or who is alleged to have violated (if there is evidence that the alleged violation has been repeated) or to be in violation of any condition of such permit.The district courts shall have jurisdiction, without regard to the amount in controversy or the citizenship of the parties, to enforce such an emission standard or limitation, or such an order, or to order the Administrator to perform such act or duty, as the case may be, and to apply any appropriate civil penalties (except for actions under paragraph (2)). The district courts of the United States shall have jurisdiction to compel (consistent with paragraph (2) of this subsection) agency action unreasonably delayed, except that an action to compel agency action referred to in section 7607(b) of this title which is unreasonably delayed may only be filed in a United States District Court within the circuit in which such action would be reviewable under section 7607(b) of this title. In any such action for unreasonable delay, notice to the entities referred to in subsection (b)(1)(A) shall be provided 180 days before commencing such action.
-
(1) Upon petition by the governor1 of Guam, American Samoa, the Virgin Islands, or the Commonwealth of the Northern Mariana Islands, the Administrator is authorized to exempt any person or source or class of persons or sources in such territory from any requirement under this chapter other than section 7412 of this title or any requirement under section 7410 of this title or part D2 necessary to attain or maintain a national primary ambient air quality standard. Such exemption may be granted if the Administrator finds that compliance with such requirement is not feasible or is unreasonable due to unique geographical, meteorological, or economic factors of such territory, or such other local factors as the Administrator deems significant. Any such petition shall be considered in accordance with section 7607(d) of this title and any exemption under this subsection shall be considered final action by the Administrator for the purposes of section 7607(b) of this title.
Citations to §7607(d)
-
(3) Section 7607(d) of this title shall apply to any high altitude regulation referred to in paragraph (2) and before promulgating any such regulation, the Administrator shall consider and make a finding with respect to—(A) the economic impact upon consumers, individual high altitude dealers, and the automobile industry of any such regulation, including the economic impact which was experienced as a result of the regulation imposed during model year 1977 with respect to high altitude certification requirements;(B) the present and future availability of emission control technology capable of meeting the applicable vehicle and engine emission requirements without reducing model availability; and(C) the likelihood that the adoption of such a high altitude regulation will result in any significant improvement in air quality in any area to which it shall apply.
-
(1) The Administrator is authorized to prescribe such regulations as are necessary to carry out his functions under this chapter. The Administrator may delegate to any officer or employee of the Environmental Protection Agency such of his powers and duties under this chapter, except the making of regulations subject to section 7607(d) of this title, as he may deem necessary or expedient.
-
(1) Upon petition by the governor1 of Guam, American Samoa, the Virgin Islands, or the Commonwealth of the Northern Mariana Islands, the Administrator is authorized to exempt any person or source or class of persons or sources in such territory from any requirement under this chapter other than section 7412 of this title or any requirement under section 7410 of this title or part D2 necessary to attain or maintain a national primary ambient air quality standard. Such exemption may be granted if the Administrator finds that compliance with such requirement is not feasible or is unreasonable due to unique geographical, meteorological, or economic factors of such territory, or such other local factors as the Administrator deems significant. Any such petition shall be considered in accordance with section 7607(d) of this title and any exemption under this subsection shall be considered final action by the Administrator for the purposes of section 7607(b) of this title.
Citations to §7607(d)(2)
-
(b) Before publication of notice of proposed rulemaking with respect to any standard or regulation to which this section applies, the Administrator shall prepare an economic impact assessment respecting such standard or regulation. Such assessment shall be included in the docket required under section 7607(d)(2) of this title and shall be available to the public as provided in section 7607(d)(4) of this title. Notice of proposed rulemaking shall include notice of such availability together with an explanation of the extent and manner in which the Administrator has considered the analysis contained in such economic impact assessment in proposing the action. The Administrator shall also provide such an explanation in his notice of promulgation of any regulation or standard referred to in subsection (a). Each such explanation shall be part of the statements of basis and purpose required under sections 7607(d)(3) and 7607(d)(6) of this title.
Citations to §7607(d)(3)
-
(b) Before publication of notice of proposed rulemaking with respect to any standard or regulation to which this section applies, the Administrator shall prepare an economic impact assessment respecting such standard or regulation. Such assessment shall be included in the docket required under section 7607(d)(2) of this title and shall be available to the public as provided in section 7607(d)(4) of this title. Notice of proposed rulemaking shall include notice of such availability together with an explanation of the extent and manner in which the Administrator has considered the analysis contained in such economic impact assessment in proposing the action. The Administrator shall also provide such an explanation in his notice of promulgation of any regulation or standard referred to in subsection (a). Each such explanation shall be part of the statements of basis and purpose required under sections 7607(d)(3) and 7607(d)(6) of this title.
Citations to §7607(d)(4)
-
(b) Before publication of notice of proposed rulemaking with respect to any standard or regulation to which this section applies, the Administrator shall prepare an economic impact assessment respecting such standard or regulation. Such assessment shall be included in the docket required under section 7607(d)(2) of this title and shall be available to the public as provided in section 7607(d)(4) of this title. Notice of proposed rulemaking shall include notice of such availability together with an explanation of the extent and manner in which the Administrator has considered the analysis contained in such economic impact assessment in proposing the action. The Administrator shall also provide such an explanation in his notice of promulgation of any regulation or standard referred to in subsection (a). Each such explanation shall be part of the statements of basis and purpose required under sections 7607(d)(3) and 7607(d)(6) of this title.
Citations to §7607(d)(6)
-
(b) Before publication of notice of proposed rulemaking with respect to any standard or regulation to which this section applies, the Administrator shall prepare an economic impact assessment respecting such standard or regulation. Such assessment shall be included in the docket required under section 7607(d)(2) of this title and shall be available to the public as provided in section 7607(d)(4) of this title. Notice of proposed rulemaking shall include notice of such availability together with an explanation of the extent and manner in which the Administrator has considered the analysis contained in such economic impact assessment in proposing the action. The Administrator shall also provide such an explanation in his notice of promulgation of any regulation or standard referred to in subsection (a). Each such explanation shall be part of the statements of basis and purpose required under sections 7607(d)(3) and 7607(d)(6) of this title.