US Codex
U.S.C.
Notes

§702c. Expenditures for construction work; conditions precedent; liability for damage from flood waters; condemnation proceedings; floodage rights — Inbound Citations

33 U.S.C. § 702c

Cited by 5 provisions in release 119-102.

Citations to 33 U.S.C. § 702c as a whole

  • (a) The existing engineering plan for flood control in the alluvial valley of the Mississippi River is modified so as to provide for the construction of plan 4 as set forth in the report of the Mississippi River Commission, dated March 7, 1941, to the Chief of Engineers, except that the levees in the Yazoo Basin on the east bank of the Mississippi River south of the Coahoma-Bolivar County line in said plan shall have a three foot freeboard over the project flood, and all levees shall be constructed with adequate section and foundation to conform to increased levee heights. The Boeuf Floodway in the project adopted by sections 702a, 702b to 702d, 702e to 702g, 702h, 702i, 702j, 702k, 702l, 702m, and 704 of this title, and the Eudora Floodway as well as the Northward Extension and the back protection levee extending from the head of the said Eudora Floodway north to the Arkansas River in the project adopted by sections 642a, 702a–1, 702a–2 to 702a–12, 702g–1, 702j–1, 702j–2, 702k–1, and 702k–2 of this title, are abandoned, and the provisions of said sections relating to the prosecution of work on said floodways and extension are repealed; except that the Ouachita River Levees, Louisiana, authorized by section 702a of this title, shall remain as a component of the Mississippi River and Tributaries Project and afforded operation and maintenance responsibilities as provided under section 702c of this title.
  • (b) The project for flood control of the Yazoo River shall be as authorized by sections 642a, 702a–1, 702a–2 to 702a–12, 702g–1, 702j–1, 702j–2, 702k–1, and 702k–2 of this title, except that the Chief of Engineers may, in his discretion, from time to time, substitute therefor combinations of reservoirs, levees, and channel improvements; and except that the extension of the authorized project and improvements contemplated in plan C of the report of March 7, 1941, of the Mississippi River Commission are authorized, including the extension of the levee on the east bank of the Mississippi River generally along the west bank of the Yazoo River to a connection in the vicinity of Yazoo City with the Yazoo River levee, authorized by the existing project for protection against headwater floods of the Yazoo River system, and the adjustment in the discretion of the Chief of Engineers of the grades of the existing levees in the backwater area on the east bank of Yazoo River below Yazoo City, all at an estimated additional cost of $11,982,000: Provided, That the Chief of Engineers shall fix the grade of the extension levees along the Yazoo River, with higher levees in his discretion, so that their construction will give the maximum practical protection without jeopardizing the safety and integrity of the main Mississippi River levees: And provided further, That prior to the beginning of construction local authorities shall furnish satisfactory assurances that they will (1) maintain the levees in accordance with the provisions of section 702c of this title, and will (2) not raise the levees in the backwater above the limiting elevations established therefor by the Chief of Engineers.
  • (c) In the development of the authorized project, the construction of a levee and improvements contemplated in the report of March 7, 1941, of the Mississippi River Commission from the main-line levee on the west bank of the Mississippi River in the vicinity of Shaw, Louisiana, westward and northward to the vicinity of Newlight, Louisiana, for the protection of that part of the Red River backwater known as the Tensas-Cocodrie area at an estimated cost of $6,976,000 is authorized: Provided, That the Chief of Engineers shall fix the grade of said levee, with a higher levee in his discretion, so that its construction will give the maximum practical protection without jeopardizing the safety and integrity of the main Mississippi River levees: And provided further, That prior to the beginning of construction local authorities shall furnish satisfactory assurances that they will (1) maintain the levee in accordance with the provisions of section 702c of this title, and will (2) not raise the said levee above the limiting elevations established therefor by the Chief of Engineers: Provided further, That subject to the foregoing conditions of local cooperation the Chief of Engineers may in his discretion substitute other levees and appurtenant works for, or make such modifications of, the levees and improvements herein authorized for the protection of the Tensas-Cocodrie area as may be found after further investigation to afford protection to a larger area in the Red River Backwater at a total cost not to exceed $29,000,000 and without jeopardizing the safety and integrity of the main Mississippi River levees and without preventing or jeopardizing the diversions contemplated in the adopted project through the Atchafalaya River and Atchafalaya Basin.
  • (1) Nothing in this chapter shall alter or affect in any way the provisions of section 702c of title 33.
  • (2) The Secretary shall provide notice of the provisions of section 702c of title 33 and this chapter to all existing and prospective lessees of lands leased by the United States and within the Colorado River Floodway.