§2282. Feasibility reports — Inbound Citations
33 U.S.C. § 2282
Cited by 12 provisions in release 119-102.
Citations to 33 U.S.C. § 2282 as a whole
-
(A) a feasibility report developed under section 2282 of this title;
-
(2) The term “feasibility study” means a study that results in a feasibility report under section 2282 of this title, and any associated environmental impact statement and mitigation plan, prepared by the Corps of Engineers for a water resources project. The term includes a study that results in a project implementation report prepared under title VI of the Water Resources Development Act of 2000 (114 Stat. 2680–2694), a general reevaluation report, and a limited reevaluation report.
-
(iii) for a qualifying project without a completed feasibility report in accordance with section 2282 of this title, prior to the completion of such a report; and
-
(iv) for a qualifying project with a completed feasibility report in accordance with section 2282 of this title that has not yet been authorized, during design for the qualifying project.
-
(1) At the request of a non-Federal interest for an assessment completed under this section, the Secretary is authorized to prepare a feasibility report, in accordance with the requirements of section 2282 of this title, recommending the construction or modification of a water resources development project to address a water resources need of a river basin or watershed of the United States identified in the assessment.
-
(A) The term “feasibility report” means a final feasibility report developed under section 2282 of this title.
-
(1) Upon the request of a non-Federal interest, in carrying out a feasibility study for a project for flood risk mitigation, hurricane and storm damage risk reduction, or ecosystem restoration under section 2282 of this title, the Secretary shall consider whether the need for the project is predicated upon or exacerbated by conditions related to sea level rise or inland flooding.
-
(7) The term “project study” means a feasibility study for a project carried out pursuant to section 2282 of this title.
-
(5) The term “project study” means a feasibility study for a project carried out pursuant to section 2282 of this title for which a categorical exclusion may apply, or an environmental assessment or an environmental impact statement is required, pursuant to the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.).
Citations to §2282(a)
-
(a) To the extent practicable, a feasibility study initiated by the Secretary, after June 10, 2014, under section 2282(a) of this title shall—(1) result in the completion of a final feasibility report not later than 4 years after the date on which the Secretary determines the Federal interest for purposes of the report pursuant to section 2282(b) of this title;(2) have a maximum total cost of $5,000,000; and(3) ensure that personnel from the district, division, and headquarters levels of the Corps of Engineers concurrently conduct the review required under that section.
Citations to §2282(b)
-
(1) result in the completion of a final feasibility report not later than 4 years after the date on which the Secretary determines the Federal interest for purposes of the report pursuant to section 2282(b) of this title;
Citations to §2282(g)(2)
-
(ii) The plan established under clause (i) shall be incorporated into the project schedule milestones set under section 2282(g)(2) of this title.