§1265. Environmental protection performance standards — Inbound Citations
30 U.S.C. § 1265
Cited by 25 provisions in release 119-102.
Citations to 30 U.S.C. § 1265 as a whole
-
(3) The Secretary of the Interior may devise a different standard than any of those set forth in section 515 and section 516 of the Surface Mining Control and Reclamation Act of 1977 [30 U.S.C. 1265, 1266], and devise a separate permit system, if he determines, on a standard-by-standard basis, that a different standard may facilitate the on-site reprocessing, or the removal, of abandoned coal refuse in a manner that would provide the same level of environmental protection as under section 515 and section 516.
-
(c) On and after nine months from August 3, 1977, all surface coal mining operations on lands on which such operations are regulated by a State shall comply with the provisions of subsections (b)(2), (b)(3), (b)(5), (b)(10), (b)(13), (b)(15), (b)(19), and (d) of section 1265 of this title or, where a surface coal mining operation will remove an entire coal seam or seams running through the upper fraction of a mountain, ridge, or hill by removing all of the overburden and creating a level plateau or a gently rolling contour with no highwalls remaining, such operation shall comply with the requirements of section 1265(c)(4) and (5) of this title without regard to the requirements of section 1265(b)(3) or (d)(2) and (3) of this title, with respect to lands from which overburden and the coal seam being mined have not been removed: Provided, however, That surface coal mining operations in operation pursuant to a permit issued by a State before August 3, 1977, issued to a person as defined in section 1291(19) of this title in existence prior to May 2, 1977 and operated by a person whose total annual production of coal from surface and underground coal mining operations does not exceed one hundred thousand tons shall not be subject to the provisions of this subsection except with reference to the provision of section 1265(d)(1) of this title until January 1, 1979.
-
(5) the engineering techniques proposed to be used in mining and reclamation and a description of the major equipment; a plan for the control of surface water drainage and of water accumulation; a plan, where appropriate, for backfilling, soil stabilization, and compacting, grading, and appropriate revegetation; a plan for soil reconstruction, replacement, and stabilization, pursuant to the performance standards in section 1265(b)(7)(A), (B), (C), and (D) of this title, for those food, forage, and forest lands identified in section 1265(b)(7) of this title; an estimate of the cost per acre of the reclamation, including a statement as to how the permittee plans to comply with each of the requirements set out in section 1265 of this title;
-
(b) Liability under the bond shall be for the duration of the surface coal mining and reclamation operation and for a period coincident with operator’s responsibility for revegetation requirements in section 1265 of this title. The bond shall be executed by the operator and a corporate surety licensed to do business in the State where such operation is located, except that the operator may elect to deposit cash, negotiable bonds of the United States Government or such State, or negotiable certificates of deposit of any bank organized or transacting business in the United States. The cash deposit or market value of such securities shall be equal to or greater than the amount of the bond required for the bonded area.
-
(a) Each State or Federal program shall include a requirement that coal exploration operations which substantially disturb the natural land surface be conducted in accordance with exploration regulations issued by the regulatory authority. Such regulations shall include, at a minimum (1) the requirement that prior to conducting any exploration under this section, any person must file with the regulatory authority notice of intention to explore and such notice shall include a description of the exploration area and the period of supposed exploration and (2) provisions for reclamation in accordance with the performance standards in section 1265 of this title of all lands disturbed in exploration, including excavations, roads, drill holes, and the removal of necessary facilities and equipment.
-
(10) with respect to other surface impacts not specified in this subsection including the construction of new roads or the improvement or use of existing roads to gain access to the site of such activities and for haulage, repair areas, storage areas, processing areas, shipping areas, and other areas upon which are sited structures, facilities, or other property or materials on the surface, resulting from or incident to such activities, operate in accordance with the standards established under section 1265 of this title for such effects which result from surface coal mining operations: Provided, That the Secretary shall make such modifications in the requirements imposed by this paragraph as are necessary to accommodate the distinct difference between surface and underground coal mining;
-
(2) After revegetation has been established on the regraded mined lands in accordance with the approved reclamation plan. When determining the amount of bond to be released after successful revegetation has been established, the regulatory authority shall retain that amount of bond for the revegetated area which would be sufficient for a third party to cover the cost of reestablishing revegetation and for the period specified for operator responsibility in section 1265 of this title of reestablishing revegetation. No part of the bond or deposit shall be released under this paragraph so long as the lands to which the release would be applicable are contributing suspended solids to streamflow or runoff outside the permit area in excess of the requirements set by section 1265(b)(10) of this title or until soil productivity for prime farm lands has returned to equivalent levels of yield as nonmined land of the same soil type in the surrounding area under equivalent management practices as determined from the soil survey performed pursuant to section 1257(b)(16) of this title. Where a silt dam is to be retained as a permanent impoundment pursuant to section 1265(b)(8) of this title, the portion of bond may be released under this paragraph so long as provisions for sound future maintenance by the operator or the landowner have been made with the regulatory authority.
-
(3) When the operator has completed successfully all surface coal mining and reclamation activities, the release of the remaining portion of the bond, but not before the expiration of the period specified for operator responsibility in section 1265 of this title: Provided, however, That no bond shall be fully released until all reclamation requirements of this chapter are fully met.
-
(1) Any action of the Secretary to approve or disapprove a State program or to prepare or promulgate a Federal program pursuant to this chapter shall be subject to judicial review by the United States District Court for the District which includes the capital of the State whose program is at issue. Any action by the Secretary promulgating national rules or regulations including standards pursuant to sections 1251, 1265, 1266, and 1273 of this title shall be subject to judicial review in the United States District Court for the District of Columbia Circuit. Any other action constituting rulemaking by the Secretary shall be subject to judicial review only by the United States District Court for the District in which the surface coal mining operation is located. Any action subject to judicial review under this subsection shall be affirmed unless the court concludes that such action is arbitrary, capricious, or otherwise inconsistent with law. A petition for review of any action subject to judicial review under this subsection shall be filed in the appropriate Court within sixty days from the date of such action, or after such date if the petition is based solely on grounds arising after the sixtieth day. Any such petition may be made by any person who participated in the administrative proceedings and who is aggrieved by the action of the Secretary.
-
(a) The Secretary is authorized to and shall issue separate regulations according to time schedules established in this chapter for anthracite coal surface mines, if such mines are regulated by environmental protection standards of the State in which they are located. Such alternative regulations shall adopt, in each instance, the environmental protection provisions of the State regulatory program in existence on August 3, 1977, in lieu of sections 1265 and 1266 of this title. Provisions of sections 1259 and 1269 of this title are applicable except for specified bond limits and period of revegetation responsibility. All other provisions of this chapter apply and the regulation issued by the Secretary of Interior for each State anthracite regulatory program shall so reflect: Provided, however, That upon amendment of a State’s regulatory program for anthracite mining or regulations thereunder in force in lieu of the above-cited sections of this chapter, the Secretary shall issue such additional regulations as necessary to meet the purposes of this chapter.
-
(c) On and after one hundred and thirty-five days from August 3, 1977, all surface coal mining operations on Indian lands shall comply with requirements at least as stringent as those imposed by subsections (b)(2), (b)(3), (b)(5), (b)(10), (b)(13), (b)(19), and (d) of section 1265 of this title and the Secretary shall incorporate the requirements of such provisions in all existing and new leases issued for coal on Indian lands.
-
(d) On and after thirty months from August 3, 1977, all surface coal mining operations on Indian lands shall comply with requirements at least as stringent as those imposed by sections 1257, 1258, 1259, 1260, 1265, 1266, 1267, and 1269 of this title and the Secretary shall incorporate the requirements of such provisions in all existing and new leases issued for coal on Indian lands.
-
In order to encourage advances in mining and reclamation practices or to allow post-mining land use for industrial, commercial, residential, or public use (including recreational facilities), the regulatory authority with approval by the Secretary may authorize departures in individual cases on an experimental basis from the environmental protection performance standards promulgated under sections 1265 and 1266 of this title. Such departures may be authorized if (i) the experimental practices are potentially more or at least as environmentally protective, during and after mining operations, as those required by promulgated standards; (ii) the mining operations approved for particular land-use or other purposes are not larger or more numerous than necessary to determine the effectiveness and economic feasibility of the experimental practices; and (iii) the experimental practices do not reduce the protection afforded public health and safety below that provided by promulgated standards.
Citations to §1265(b)(3)
-
(c) On and after nine months from August 3, 1977, all surface coal mining operations on lands on which such operations are regulated by a State shall comply with the provisions of subsections (b)(2), (b)(3), (b)(5), (b)(10), (b)(13), (b)(15), (b)(19), and (d) of section 1265 of this title or, where a surface coal mining operation will remove an entire coal seam or seams running through the upper fraction of a mountain, ridge, or hill by removing all of the overburden and creating a level plateau or a gently rolling contour with no highwalls remaining, such operation shall comply with the requirements of section 1265(c)(4) and (5) of this title without regard to the requirements of section 1265(b)(3) or (d)(2) and (3) of this title, with respect to lands from which overburden and the coal seam being mined have not been removed: Provided, however, That surface coal mining operations in operation pursuant to a permit issued by a State before August 3, 1977, issued to a person as defined in section 1291(19) of this title in existence prior to May 2, 1977 and operated by a person whose total annual production of coal from surface and underground coal mining operations does not exceed one hundred thousand tons shall not be subject to the provisions of this subsection except with reference to the provision of section 1265(d)(1) of this title until January 1, 1979.
Citations to §1265(b)(7)
-
(5) the engineering techniques proposed to be used in mining and reclamation and a description of the major equipment; a plan for the control of surface water drainage and of water accumulation; a plan, where appropriate, for backfilling, soil stabilization, and compacting, grading, and appropriate revegetation; a plan for soil reconstruction, replacement, and stabilization, pursuant to the performance standards in section 1265(b)(7)(A), (B), (C), and (D) of this title, for those food, forage, and forest lands identified in section 1265(b)(7) of this title; an estimate of the cost per acre of the reclamation, including a statement as to how the permittee plans to comply with each of the requirements set out in section 1265 of this title;
-
(1) In addition to finding the application in compliance with subsection (b) of this section, if the area proposed to be mined contains prime farmland pursuant to section 1257(b)(16) of this title, the regulatory authority shall, after consultation with the Secretary of Agriculture, and pursuant to regulations issued hereunder by the Secretary of2 Interior with the concurrence of the Secretary of Agriculture, grant a permit to mine on prime farmland if the regulatory authority finds in writing that the operator has the technological capability to restore such mined area, within a reasonable time, to equivalent or higher levels of yield as non-mined prime farmland in the surrounding area under equivalent levels of management and can meet the soil reconstruction standards in section 1265(b)(7) of this title. Except for compliance with subsection (b), the requirements of this paragraph (1) shall apply to all permits issued after August 3, 1977.
Citations to §1265(b)(7)(A)
-
(5) the engineering techniques proposed to be used in mining and reclamation and a description of the major equipment; a plan for the control of surface water drainage and of water accumulation; a plan, where appropriate, for backfilling, soil stabilization, and compacting, grading, and appropriate revegetation; a plan for soil reconstruction, replacement, and stabilization, pursuant to the performance standards in section 1265(b)(7)(A), (B), (C), and (D) of this title, for those food, forage, and forest lands identified in section 1265(b)(7) of this title; an estimate of the cost per acre of the reclamation, including a statement as to how the permittee plans to comply with each of the requirements set out in section 1265 of this title;
Citations to §1265(b)(8)
-
(2) After revegetation has been established on the regraded mined lands in accordance with the approved reclamation plan. When determining the amount of bond to be released after successful revegetation has been established, the regulatory authority shall retain that amount of bond for the revegetated area which would be sufficient for a third party to cover the cost of reestablishing revegetation and for the period specified for operator responsibility in section 1265 of this title of reestablishing revegetation. No part of the bond or deposit shall be released under this paragraph so long as the lands to which the release would be applicable are contributing suspended solids to streamflow or runoff outside the permit area in excess of the requirements set by section 1265(b)(10) of this title or until soil productivity for prime farm lands has returned to equivalent levels of yield as nonmined land of the same soil type in the surrounding area under equivalent management practices as determined from the soil survey performed pursuant to section 1257(b)(16) of this title. Where a silt dam is to be retained as a permanent impoundment pursuant to section 1265(b)(8) of this title, the portion of bond may be released under this paragraph so long as provisions for sound future maintenance by the operator or the landowner have been made with the regulatory authority.
-
(2) “approximate original contour” means that surface configuration achieved by backfilling and grading of the mined area so that the reclaimed area, including any terracing or access roads, closely resembles the general surface configuration of the land prior to mining and blends into and complements the drainage pattern of the surrounding terrain, with all highwalls and spoil piles eliminated; water impoundments may be permitted where the regulatory authority determines that they are in compliance with section 1265(b)(8) of this title;
Citations to §1265(b)(10)
-
(2) After revegetation has been established on the regraded mined lands in accordance with the approved reclamation plan. When determining the amount of bond to be released after successful revegetation has been established, the regulatory authority shall retain that amount of bond for the revegetated area which would be sufficient for a third party to cover the cost of reestablishing revegetation and for the period specified for operator responsibility in section 1265 of this title of reestablishing revegetation. No part of the bond or deposit shall be released under this paragraph so long as the lands to which the release would be applicable are contributing suspended solids to streamflow or runoff outside the permit area in excess of the requirements set by section 1265(b)(10) of this title or until soil productivity for prime farm lands has returned to equivalent levels of yield as nonmined land of the same soil type in the surrounding area under equivalent management practices as determined from the soil survey performed pursuant to section 1257(b)(16) of this title. Where a silt dam is to be retained as a permanent impoundment pursuant to section 1265(b)(8) of this title, the portion of bond may be released under this paragraph so long as provisions for sound future maintenance by the operator or the landowner have been made with the regulatory authority.
Citations to §1265(b)(15)
-
(g) Each applicant for a surface coal mining and reclamation permit shall submit to the regulatory authority as part of the permit application a blasting plan which shall outline the procedures and standards by which the operator will meet the provisions of section 1265(b)(15) of this title.
Citations to §1265(b)(15)(E)
-
(E) Pre-blast surveys required by section 1265(b)(15)(E) of this title.
Citations to §1265(c)(4)
-
(c) On and after nine months from August 3, 1977, all surface coal mining operations on lands on which such operations are regulated by a State shall comply with the provisions of subsections (b)(2), (b)(3), (b)(5), (b)(10), (b)(13), (b)(15), (b)(19), and (d) of section 1265 of this title or, where a surface coal mining operation will remove an entire coal seam or seams running through the upper fraction of a mountain, ridge, or hill by removing all of the overburden and creating a level plateau or a gently rolling contour with no highwalls remaining, such operation shall comply with the requirements of section 1265(c)(4) and (5) of this title without regard to the requirements of section 1265(b)(3) or (d)(2) and (3) of this title, with respect to lands from which overburden and the coal seam being mined have not been removed: Provided, however, That surface coal mining operations in operation pursuant to a permit issued by a State before August 3, 1977, issued to a person as defined in section 1291(19) of this title in existence prior to May 2, 1977 and operated by a person whose total annual production of coal from surface and underground coal mining operations does not exceed one hundred thousand tons shall not be subject to the provisions of this subsection except with reference to the provision of section 1265(d)(1) of this title until January 1, 1979.
Citations to §1265(d)(1)
-
(c) On and after nine months from August 3, 1977, all surface coal mining operations on lands on which such operations are regulated by a State shall comply with the provisions of subsections (b)(2), (b)(3), (b)(5), (b)(10), (b)(13), (b)(15), (b)(19), and (d) of section 1265 of this title or, where a surface coal mining operation will remove an entire coal seam or seams running through the upper fraction of a mountain, ridge, or hill by removing all of the overburden and creating a level plateau or a gently rolling contour with no highwalls remaining, such operation shall comply with the requirements of section 1265(c)(4) and (5) of this title without regard to the requirements of section 1265(b)(3) or (d)(2) and (3) of this title, with respect to lands from which overburden and the coal seam being mined have not been removed: Provided, however, That surface coal mining operations in operation pursuant to a permit issued by a State before August 3, 1977, issued to a person as defined in section 1291(19) of this title in existence prior to May 2, 1977 and operated by a person whose total annual production of coal from surface and underground coal mining operations does not exceed one hundred thousand tons shall not be subject to the provisions of this subsection except with reference to the provision of section 1265(d)(1) of this title until January 1, 1979.
Citations to §1265(f)
-
(5) design, locate, construct, operate, maintain, enlarge, modify, and remove, or abandon, in accordance with the standards and criteria developed pursuant to section 1265(f) of this title, all existing and new coal mine waste piles consisting of mine wastes, tailings, coal processing wastes, or other liquid and solid wastes and used either temporarily or permanently as dams or embankments;