§4374. Unit cost reports: determinations by service acquisition executive and secretary concerned of breach of significant cost growth threshold or critical cost growth threshold; reports to Congress — Inbound Citations
10 U.S.C. § 4374
Cited by 9 provisions in release 119-102.
Citations to 10 U.S.C. § 4374 as a whole
-
(C) The system being acquired pursuant to such contract has not been determined to have experienced cost growth in excess of the critical cost growth threshold pursuant to section 4374 of this title within 5 years prior to the date the Secretary anticipates such contract (or a contract for advance procurement entered into consistent with the authorization for such contract) will be awarded.
-
(i) any acquisition program for which, since the last such announcement, the Secretary concerned has determined under section 4374 of this title that the program’s acquisition unit cost or procurement unit cost has increased by a percentage equal to or greater than the critical cost growth threshold for the program (in this section referred to as a “critical cost growth threshold breach”);
-
(2) An adjustment or revision of the original baseline description of a major defense acquisition program or any designated major subprogram under the program may be treated as the original Baseline Estimate for the program or subprogram for purposes of this chapter only if the percentage increase in the program acquisition unit cost or procurement unit cost under such adjustment or revision exceeds the critical cost growth threshold for the program or subprogram under sections 4371 through 4375 of this title, as determined by the Secretary of the military department concerned under section 4374 of this title.
-
(1) Except as provided in paragraph (2), whenever the Secretary concerned determines under section 4374 of this title that the program acquisition unit cost or the procurement unit cost of a major defense acquisition program or designated major subprogram has increased by a percentage equal to or greater than the significant cost growth threshold for the program or subprogram, a Selected Acquisition Report shall be submitted to Congress for the first fiscal-year quarter ending on or after the date of the determination or for the fiscal-year quarter which immediately precedes the first fiscal-year quarter ending on or after that date. The report shall include the information described in section 4351(e) of this title and shall be submitted in accordance with section 4351(f) of this title.
-
(b) If the program acquisition unit cost or procurement unit cost of a major defense acquisition program or designated major subprogram (as determined by the Secretary under section 4374 of this title) increases by a percentage equal to or greater than the critical cost growth threshold for the program or subprogram, the Secretary of Defense shall take actions consistent with the requirements of sections 4376 and 4377 of this title.
-
(1) If a determination of an increase by a percentage equal to or greater than the significant cost growth threshold is made by the Secretary under section 4374 of this title and a Selected Acquisition Report containing the information described in subsection (d) is not submitted to Congress under subsection (a), or if a determination of an increase by a percentage equal to or greater than the critical cost growth threshold is made by the Secretary under section 4374 of this title and the certification of the Secretary of Defense is not submitted to Congress under subsection (b), funds appropriated for military construction, for research, development, test, and evaluation, and for procurement may not be obligated for a major contract under the program.
-
(A) on which Congress receives the Selected Acquisition Report under subsection (a) with respect to that program, in the case of a determination of an increase by a percentage equal to or greater than the significant cost growth threshold (as determined in section 4374 of this title); or
-
(B) on which Congress has received both the Selected Acquisition Report under subsection (a) and the certification of the Secretary of Defense under section 4376 with respect to that program, in the case of an increase by a percentage equal to or greater than the critical cost growth threshold (as determined under section 4374 of this title).
-
(a) If the program acquisition unit cost or procurement unit cost of a major defense acquisition program or designated subprogram (as determined by the Secretary under section 4374 of this title) increases by a percentage equal to or greater than the critical cost growth threshold for the program or subprogram, the Secretary of Defense shall—(1) determine the root cause or causes of the critical cost growth in accordance with applicable statutory requirements and Department of Defense policies, procedures, and guidance; and(2) in consultation with the Director of Cost Assessment and Program Evaluation, carry out an assessment of—(A) the projected cost of completing the program if current requirements are not modified;(B) the projected cost of completing the program based on reasonable modification of such requirements;(C) the rough order of magnitude of the costs of any reasonable alternative system or capability; and