# §1753.79. Construction by force account.


The borrower shall require that:

- (a) **Minor construction by the force account method be supervised by a competent foreman.** The work shall be performed in accordance with all regulatory and safety codes.
- (b) Daily time and material reports, referenced by the work project number, shall be kept to record labor and materials used as construction is performed.
- (c) The construction foreman shall maintain a tabulation of all construction units installed.