# §633.19. Exclusion from the project management oversight program.


The Administrator may, in compelling circumstances, determine that a project meeting the criteria of [§ 633.5(e)(1)](/cfr/49/633.5.md?p=e-1) is not a major capital project because project management oversight under this part will not benefit the Federal government or the recipient. Typically, this means a project that:

- (a) Involves a recipient whose past record indicates the appropriateness of excluding the project from project management oversight under this part; and
- (b) Involves such a greater level of financial risk to the recipient than to the Federal government that project management oversight under this part is made less necessary to secure the recipient's diligence.

## Notes

### Authority

Authority: 49 U.S.C. 5327; 49 U.S.C. 5334; 49 CFR 1.91.

### Source

Source: 85 FR 59679, Sept. 23, 2020, unless otherwise noted.