# §381.510. May the FMCSA end a pilot program before its scheduled completion date?


The FMCSA will immediately terminate a pilot program if there is reason to believe the program is not achieving a level of safety that is at least equivalent to the level of safety that would be achieved by complying with the regulations.


## Notes

### Authority

Authority: 49 U.S.C. 31136(e), 31315; and 49 CFR 1.87.

### Source

Source: 63 FR 67608, Dec. 8, 1998, unless otherwise noted.