# §299.711. Inspection, testing, and maintenance program format.


The submission to FRA for each identified subsystem shall consist of two parts—

- (a) The complete inspection, testing, and maintenance program, in its entirety, including all required information prescribed in [§ 299.701](/cfr/49/299.701.md), and all information and procedures required for the railroad and its personnel to implement the program.
- (b) A condensed version of the program that contains only those items identified as safety-critical, per [§ 299.703](/cfr/49/299.703.md) submitted for approval by FRA under [§ 299.713](/cfr/49/299.713.md).

## Notes

### Authority

Authority: 49 U.S.C. 20103, 20107, 20133, 20141, 20302-20303, 20306, 20701-20702, 21301-21302, 21304; 28 U.S.C. 2461, note; and 49 CFR 1.89.

### Source

Source: 85 FR 69731, Nov. 3, 2020, unless otherwise noted.