# §536.7106. Construction contract closeout.


Unless the contract has been converted to a standard firm-fixed-price contract (see 536.7105-8)—

- (a) The contracting officer shall ensure that the construction contractor's proposal for final settlement is accurate and reliable in accordance with the open book accounting practices of the contract.
- (b) In accordance with 536.7105-3(c), the contracting officer shall obtain an independent audit of the construction contractor's costs.