# §49.402-7. Other damages.

- (a) If the contracting officer terminates a contract for default or follows a course of action instead of termination for default (see 49.402-4), the contracting officer promptly must assess and demand any liquidated damages to which the Government is entitled under the contract. Under the contract clause at 52.211-11, these damages are in addition to any excess repurchase costs.
- (b) If the Government has suffered any other ascertainable damages, including administrative costs, as a result of the contractor's default, the contracting officer must, on the basis of legal advice, take appropriate action as prescribed in [subpart 32.6](/cfr/48/subpart32.6.md) to assert the Government's demand for the damages.

## Notes

### Amendments

[48 FR 42447, Sept. 19, 1983, as amended at 56 FR 15154, Apr. 15, 1991; 60 FR 48250, Sept. 18, 1995; 65 FR 46066, July 26, 2000]

### Authority

Authority: 40 U.S.C. 121(c); 10 U.S.C. chapter 4 and 10 U.S.C. chapter 137 legacy provisions (see 10 U.S.C. 3016); and 51 U.S.C. 20113.

### Source

Source: 48 FR 42447, Sept. 19, 1983, unless otherwise noted.

### Amendments

[48 FR 42447, Sept. 19, 1983, as amended at 56 FR 15154, Apr. 15, 1991; 60 FR 48250, Sept. 18, 1995; 65 FR 46066, July 26, 2000]