# §36.206. Liquidated damages.


The contracting officer must evaluate the need for liquidated damages in a construction contract in accordance with 11.502 and agency regulations.


## Notes

### Amendments

[48 FR 42356, Sept. 19, 1983, as amended at 60 FR 48249, Sept. 18, 1995; 65 FR 46066, July 26, 2000]

### Authority

Authority: 41 U.S.C. 1121(b); 40 U.S.C. 121(c); 10 U.S.C. chapter 4 and 10 U.S.C. chapter 137 legacy provisions (see 10 U.S.C. 3016); and 51 U.S.C. 20113.

### Source

Source: 48 FR 42356, Sept. 19, 1983, unless otherwise noted.

### Amendments

[48 FR 42356, Sept. 19, 1983, as amended at 60 FR 48249, Sept. 18, 1995; 65 FR 46066, July 26, 2000]