# §2822.103-4. Approvals.


During contract performance, contractor requests for overtime exceeding the amount authorized in paragraph (a) of the clause at FAR 52.222-2, Payment for Overtime Premiums, must be approved at a level above the contracting officer. Such approval should be reflected by the signature of the approving official on the contracting officer's written determination made in accordance with FAR 22.103-4.


## Notes

### Authority

Authority: 28 U.S.C. 510; 40 U.S.C. 486(c); 28 CFR 0.75(j) and 0.76(j).

### Source

Source: 87 FR 47118, Aug. 2, 2022, unless otherwise noted.