# §1843.205. Contract clauses.


As authorized in the prefaces of clauses FAR 52.243-1, Changes—Fixed Price; FAR 52.243-2, Changes—Cost Reimbursement; and FAR 52.243-4, Changes; and in the prescription at 43.205(c) for FAR 52.243-3, Changes—Time-and-Material or Labor-Hours, the period within which a contractor must assert its right to an equitable adjustment may be varied not to exceed 60 calendar days.


## Notes

### Amendments

[65 FR 58932, Oct. 3, 2000]

### Authority

Authority: 51 U.S.C. 20113(a) and 48 CFR chapter 1.

### Source

Source: 62 FR 14022, Mar. 25, 1997, unless otherwise noted.

### Amendments

[65 FR 58932, Oct. 3, 2000]