# §22.946. Construction period for Unserved Area authorizations.


The construction period applicable to new or modified Cellular facilities for which an authorization is granted pursuant to the Unserved Area process is one year, beginning on the date the authorization is granted. To satisfy this requirement, a Cellular system must be providing service to mobile stations operated by subscribers and roamers. The licensee must notify the FCC (FCC Form 601) after the requirements of this section are met. See [§ 1.946](/cfr/47/1.946.md) of this chapter. See also [§ 22.949](/cfr/47/22.949.md).


## Notes

### Amendments

[79 FR 72151, Dec. 5, 2014]

### Authority

Authority: 47 U.S.C. 154, 222, 303, 309, and 332.

### Source

Source: 59 FR 59507, Nov. 17, 1994, unless otherwise noted.

### Amendments

[79 FR 72151, Dec. 5, 2014]