# §3276.13. What additional information must I give BLM in the monthly report for flash and dry steam facilities?


In addition to the regular monthly report information required by [§ 3276.12](/cfr/43/3276.12.md), send to BLM:

- (a) Steam flow into the turbine in klbs; for dual flash facilities, you must separate the steam flow into high pressure steam and low pressure steam;
- (b) Condenser pressure in psia;
- (c) **Condenser temperature in deg.** F;
- (d) Auxiliary steam flow used for gas ejectors, steam seals, pumps, etc., in klbs;
- (e) Flow of condensate out of the plant (after the cooling towers) in klbs; and
- (f) Any other information we may require.