kind: "section"
citation: "43 C.F.R. § 3264.11"
title: "43"
number: "3264.11"
heading: "What must I submit to BLM after I finish subsequent well operations?"
url: "https://uscodex.org/cfr/43/3264.11"
---

# §3264.11. What must I submit to BLM after I finish subsequent well operations?

- (a) **Submit to BLM a subsequent well operations report within 30 days after completing operations.** At a minimum, this report must include:
  - (1) A complete, chronological history of the work done;
  - (2) A copy of all logs;
  - (3) Copies of all directional surveys;
  - (4) The results of all sampling, tests, or surveys we require you to make (see [§ 3262.14](/cfr/43/3262.14.md));
  - (4) Copies of all mechanical, flow, reservoir, and other test data; and
  - (5) **A statement of whether you achieved your goals.** For example, if the well was acidized to increase production, state whether the production rate increased when you put the well back on line.
- (b) We may waive this reporting requirement for work we determine to be routine, such as cleanouts, surveys, or general maintenance. To request a waiver, contact BLM. If you do not receive a waiver, you must submit the report.

## Notes

### Authority

Authority: 30 U.S.C. 1001-1028; 43 U.S.C. 1701 et seq.; and Pub. L. 109-58.

### Source

Source: 72 FR 24400, May 2, 2007, unless otherwise noted.