# §3105.21. Where filed.

- (a) An application to form a communitization agreement or modify an existing agreement must be filed with the proper BLM office for final approval.
- (b) An application for a communitization agreement must include:
  - (1) A statement as to whether the proposed communitization agreement deviates from the BLM's current model communitization agreement form, and a certification that the applicant received the required signatures;
  - (2) An Exhibit A displaying a map of the area covered by the proposed agreement and the separate agreement tracts; and
  - (3) An Exhibit B displaying the separate tracts and ownership;
- (c) To ensure accurate reporting to ONRR, an application for a communitization agreement should be submitted at least 90 calendar days prior to first production.
- (d) An application for designations of successor operator for a communitization agreement must include the processing fee found in the fee schedule in [§ 3000.120](/cfr/43/3000.120.md) of this chapter.