# §10005.16. Plan content.

- (a) **Minimum requirements.** At a minimum, the plan will include:
  - (1) A summary of basic information from the planning rule, including project evaluation procedures and plan amendment procedures,
  - (2) The identification of measurable objectives for the term of the plan,
  - (3) **A list, and description, of the projects selected for implementation during the term of the plan—** with particular emphasis on projects to be implemented early in the planning cycle,
  - (4) A description of the relationship between the projects to be included in the plan and the Commission's mitigation obligations,
  - (5) A preliminary determination regarding environmental review requirements for each project,
  - (6) A preliminary determination of management and operation requirements and how these will be met,
  - (7) A budget, both for the next fiscal year and for the entire five-year period,
  - (8) A project phasing plan spanning the term of the plan, and
  - (9) A strategy for monitoring progress and evaluating accomplishments, and
- (b) **Potential additions.** At the Commission's discretion, the plan may also include:
  - (1) A discussion of the relationship of the plan to other activities affecting fish, wildlife, and recreation resources within the State of Utah, and/or
  - (2) **Discussions of, or information on, other topics that the Commission determines to be relevant.** For example, the Commission may wish to identify mitigation and/or conservation measures that the Commission may wish to consider in later years of the five-year plan or in subsequent five-year plans.