# §405.930. Failure to respond to additional documentation request.


If a contractor gives a provider or supplier notice and time to respond to an additional documentation request and the provider or supplier does not provide the additional documentation in a timely manner, the contractor has authority to deny the claim.


## Notes

### Amendments

[86 FR 65660, Nov. 19, 2021]

### Source

Source: 70 FR 11472, Mar. 8, 2005, unless otherwise noted.

### Authority

Authority: 42 U.S.C. 263a, 405(a), 1302, 1320b-12, 1395x, 1395y(a), 1395ff, 1395hh, 1395kk, 1395rr, and 1395ww(k).

### Amendments

[86 FR 65660, Nov. 19, 2021]