# §137.343. What happens to funds remaining at the conclusion of a fixed price construction project?

- (a) For lump sum fixed price construction project agreements, all funds remaining at the conclusion of the project are considered profits and belong to the Self-Governance Tribe.
- (b) For fixed price construction project agreements with unit price components, all funds remaining that are associated with overestimated unit price quantities are savings and may be used by the Self-Governance Tribe in accordance with [section 137.342](/cfr/42/137.342.md). All other funds remaining at the conclusion of the project are considered profit and belong to the Self-Governance Tribe.
- (c) At the option of the Self-Governance Tribe, funds otherwise identified in paragraphs [(a)](#a) and [(b)](#b) as “profit” may be reclassified, in whole or in part, as savings and to that extent may be used by the Self-Governance Tribe in accordance with [section 137.142](/cfr/42/137.142.md).

## Notes

### Authority

Authority: 25 U.S.C. 458 et seq.

### Source

Source: 67 FR 35342, May 17, 2002, unless otherwise noted.