kind: "section"
citation: "40 C.F.R. § 63.5541"
title: "40"
number: "63.5541"
heading: "When must I conduct subsequent performance tests?"
url: "https://uscodex.org/cfr/40/63.5541"
---

# §63.5541. When must I conduct subsequent performance tests?

- (a) For each affected source utilizing a non-recovery control device to comply with [§ 63.5515](/cfr/40/63.5515.md) that commenced construction or reconstruction before September 9, 2019, a periodic performance test must be performed by July 2, 2023, and subsequent tests no later than 60 months thereafter.
- (b) For each affected source utilizing a non-recovery control device to comply with [§ 63.5515](/cfr/40/63.5515.md) that commences construction or reconstruction after September 9, 2019, a periodic performance test must be performed no later than 60 months after the initial performance test required by [§ 63.5535](/cfr/40/63.5535.md), and subsequent tests no later than 60 months thereafter.

## Notes

### Amendments

[85 FR 39995, July 2, 2020]

### Source

Source: 67 FR 40055, June 11, 2002, unless otherwise noted.

### Authority

Authority: 42 U.S.C. 7401 et seq.

### Source

Source: 57 FR 61992, Dec. 29, 1992, unless otherwise noted.

### Amendments

[85 FR 39995, July 2, 2020]