# §63.1945. When do I have to comply with this subpart?

- (a) If your landfill is a new affected source, you must comply with this subpart by January 16, 2003, or at the time you begin operating, whichever is later.
- (b) If your landfill is an existing affected source, you must comply with this subpart by January 16, 2004.

## Notes

### Source

Source: 85 FR 17261, Mar. 26, 2020, unless otherwise noted.

### Authority

Authority: 42 U.S.C. 7401 et seq.

### Source

Source: 57 FR 61992, Dec. 29, 1992, unless otherwise noted.