# §63.11623. What are the testing requirements?

- (a) If you are demonstrating that the cyclone required by [§ 63.11621(e)](/cfr/40/63.11621.md?p=e) is designed to reduce emissions of particulate matter by 95 percent or greater by the performance test option in [§ 63.11621(e)(1)(iii)](/cfr/40/63.11621.md?p=e-1-iii), you must conduct a test in accordance with [paragraph (b)](#b) of this section and calculate the percent reduction in accordance with [paragraph (c)](#c) of this section.
- (b) You must use Method 5 in Appendix A to [part 60](/cfr/40/part60.md) to determine the particulate matter mass rate at the inlet and outlet of the cyclone. You must conduct at least three runs at the cyclone inlet and three runs at the cyclone outlet. Each run must have a sampling time of at least 60 minutes and a sample volume of at least 0.85 dscm (30 dscf).
- (c) You must calculate the percent particulate matter reduction using Equation 1.

## Notes

### Source

Source: 75 FR 546, Jan. 5, 2010, unless otherwise noted.

### Authority

Authority: 42 U.S.C. 7401 et seq.

### Source

Source: 57 FR 61992, Dec. 29, 1992, unless otherwise noted.